Flow Shop Scheduling with Shortening Jobs for Makespan Minimization

被引:1
|
作者
Sun, Zheng-Wei [1 ]
Lv, Dan-Yang [2 ,3 ]
Wei, Cai-Min [4 ]
Wang, Ji-Bo [1 ]
机构
[1] Shenyang Aerosp Univ, Sch Comp, Shenyang 110136, Peoples R China
[2] Shenyang Aerosp Univ, Sch Mechatron Engn, Shenyang 110136, Peoples R China
[3] Shenyang Aerosp Univ, Key Lab Rapid Dev & Mfg Technol Aircraft, Minist Educ, Shenyang 110136, Peoples R China
[4] Shantou Univ, Sch Math & Comp, Shantou 515063, Peoples R China
关键词
scheduling; flow shop; shortening job; makespan; branch-and-bound algorithm; heuristic algorithm; TOTAL COMPLETION-TIME; SOLUTION ALGORITHMS; DETERIORATING JOBS; COMPLEXITY;
D O I
10.3390/math13030363
中图分类号
O1 [数学];
学科分类号
0701 ; 070101 ;
摘要
This paper deals with a two-machine flow shop problem with shortening jobs. A shortening job means that the job's processing time is a decreasing function of its starting time. The aim is to find a sequence that minimizes the makespan of all the jobs. several dominance properties, some lower bounds, and an initial upper bound are derived, which are applied to propose a branch-and-bound algorithm to solve the problem. We also propose some heuristics and mathematical programming. Computational experiments are conducted to evaluate the performance of the proposed algorithms.
引用
收藏
页数:23
相关论文
共 50 条
  • [1] MAKESPAN MINIMIZATION ON THREE-MACHINE FLOW SHOP WITH DETERIORATING JOBS
    Wang, Ji-Bo
    Wang, Ming-Zheng
    ASIA-PACIFIC JOURNAL OF OPERATIONAL RESEARCH, 2013, 30 (06)
  • [2] Flow shop makespan minimization scheduling with deteriorating jobs under dominating machines
    Sun, Lin-Hui
    Sun, Lin-Yan
    Wang, Ming-Zheng
    Wang, Ji-Bo
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2012, 138 (01) : 195 - 200
  • [3] On three-machine flow shop scheduling with deteriorating jobs
    Wang, Ling
    Sun, Lin-Yan
    Sun, Lin-Hui
    Wang, Ji-Bo
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2010, 125 (01) : 185 - 189
  • [4] An efficient hybrid heuristic for makespan minimization in permutation flow shop scheduling
    Dipak Laha
    Uday Kumar Chakraborty
    The International Journal of Advanced Manufacturing Technology, 2009, 44 : 559 - 569
  • [5] An efficient hybrid heuristic for makespan minimization in permutation flow shop scheduling
    Laha, Dipak
    Chakraborty, Uday Kumar
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2009, 44 (5-6) : 559 - 569
  • [6] Flow shop scheduling with deteriorating jobs under dominating machines to minimize makespan
    Wang, Ji-Bo
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2010, 48 (5-8) : 719 - 723
  • [7] Flow shop scheduling with deteriorating jobs under dominating machines to minimize makespan
    Ji-Bo Wang
    The International Journal of Advanced Manufacturing Technology, 2010, 48 : 719 - 723
  • [8] Testing the Performance of Bat-Algorithm for Permutation Flow Shop Scheduling Problems with Makespan Minimization
    Bellabai, Jeen Robert
    Leela, Brabin Nivas Murugadhas
    Kennedy, Senthil Maharaj Ramesh
    BRAZILIAN ARCHIVES OF BIOLOGY AND TECHNOLOGY, 2022, 65
  • [9] Makespan Minimization for Flow Shop Scheduling Problems Using Modified Operators in Genetic Algorithm
    Mumtaz, Jabir
    Guan Zailin
    Mirza, Jahanzaib
    Rauf, Mudassar
    Sarfraz, Shoaib
    Shehab, Essam
    ADVANCES IN MANUFACTURING TECHNOLOGY XXXII, 2018, 8 : 435 - 440
  • [10] Scheduling Three-Operation Jobs in a Two-Machine Flow Shop to Minimize Makespan
    Jatinder N.D. Gupta
    Christos P. Koulamas
    George J. Kyparisis
    Chris N. Potts
    Vitaly A. Strusevich
    Annals of Operations Research, 2004, 129 : 171 - 185