Mitigating strength loss in mortar due to application delay: quantified impact of additional water and cement

被引:0
作者
H. M. A. Mahzuz [1 ]
Imran Hossain [1 ]
Nasir Uddin Ahammed Lizon [1 ]
Ahmad Hasan Nury [1 ]
机构
[1] Department of Civil and Environmental Engineering, SUST, Sylhet
来源
Journal of Engineering and Applied Science | 2025年 / 72卷 / 1期
关键词
Casting delay; Compressive strength; Masonry; Mortar properties; Shear strength;
D O I
10.1186/s44147-025-00583-2
中图分类号
学科分类号
摘要
This study examines how application (i.e., “casting” another widely used term) delays affect the compressive and shear strengths of mortar in masonry constructions. It also explores the impact of adding supplementary materials like water and cement to the mortar. Mortar mixes were prepared using sand with a fineness modulus (FM) of 1.7 for plaster and 1.9 for brick binder, subjected to casting delays ranging from 0 to 4 h. Three physical conditions were utilized as follows: the 1st case—WAAW (without adding additional water); the 2nd case—AAW (adding additional water), maintaining initial mortar flow; and the 3rd case—AAWC (adding additional water and cement), maintaining initial mortar flow and initial mortar strength. In the 1st case, the fall of strength was greater than in the 2nd case. In the 3rd case, the amounts of additional cement and water were quantified to restore the initial strength of the mortar. This quantification can help avoid material loss in construction sites. © The Author(s) 2025.
引用
收藏
相关论文
共 48 条
  • [1] Uygunoglu T., Ozguven S., Calis M., Effect of plaster thickness on the performance of external thermal insulation cladding systems (ETICS) in buildings, Constr Build Mater, 122, pp. 496-504, (2016)
  • [2] Covatariu D., Toma I.O., Plesu R., Budescu M., A Study on Mortar Adherence to Masonry Pieces In Case of Historical Buildings, Proc. of ICEUBI2011–Internat. Conf. on Engng. Innovation and Development, pp. CT7-CT14, (2011)
  • [3] Zou P.X., Zhang G., Wang J., Understanding the key risks in construction projects in China, Int J Project Manage, 25, 6, pp. 601-614, (2007)
  • [4] Erdem T.K., Turanli L., Erdogan T.Y., Setting time: an important criterion to determine the length of the delay period before steam curing of concrete, Cem Concr Res, 33, 5, pp. 741-745, (2003)
  • [5] Escadeillas G., Aubert J.E., Segerer M., Prince W., Some factors affecting delayed ettringite formation in heat-cured mortars, Cem Concr Res, 37, 10, pp. 1445-1452, (2007)
  • [6] Sapkota L.P., Mishra A.K., Delay pattern assessment in concrete casting, Journal of Advanced Research in Geo Sciences and Remote Sensing, (2022)
  • [7] Cassagnabere F., Escadeillas G., Mouret M., Study of the reactivity of cement/metakaolin binders at early age for specific use in steam cured precast concrete, Constr Build Mater, 23, 2, pp. 775-784, (2009)
  • [8] Yan P., Zheng F., Peng J., Qin X., Relationship between delayed ettringite formation and delayed expansion in massive shrinkage-compensating concrete, Cement Concr Compos, 26, 6, pp. 687-693, (2004)
  • [9] Zhang M.H., Islam J., Peethamparan S., Use of nano-silica to increase early strength and reduce setting time of concretes with high volumes of slag, Cement Concr Compos, 34, 5, pp. 650-662, (2012)
  • [10] Sobhani J., Najimi M., Pourkhorshidi A.R., Effects of retempering methods on the compressive strength and water permeability of concrete, Scientia Iranica, 19, 2, pp. 211-217, (2012)