Evaluating the impact of construction delays on project duration using machine learning and multi-criteria decision analysis

被引:0
作者
Ahmed salama [1 ]
机构
[1] Civil Engineering Department, Faculty of Engineering, Ajloun National University, Ajloun
[2] Civil Engineering Department, Al-Azhar University, Nasr City, Cairo
基金
英国科研创新办公室;
关键词
Construction delays; Construction management; Jordan; Machine learning; Multi-criteria decision analysis;
D O I
10.1007/s42107-024-01196-5
中图分类号
学科分类号
摘要
Construction projects are inherently complex and prone to delays, significantly impacting project timelines and costs. This study addresses the critical issue of construction delays in Jordan by leveraging advanced methodologies such as Gaussian Process Regression (GPR) and the Analytical Hierarchy Process (AHP). The problem of accurately predicting and managing delays in construction projects has long challenged the industry, with existing approaches often failing to account for the multifaceted nature of delay factors. This research integrates GPR, a machine learning technique, with AHP, a Multi-Criteria Decision Analysis (MCDA) tool, to evaluate and predict the impact of delay factors on project duration. The study employs a comprehensive dataset comprising 191 construction projects in Jordan, with critical variables identified through expert evaluations and literature reviews. The GPR model demonstrated superior predictive capabilities, achieving an R² value close to 1, indicating its high accuracy in forecasting time and cost overruns. The AHP model, on the other hand, prioritized weather conditions and unrealistic contract requirements as the most significant contributors to delays. The findings suggest that the combined application of GPR and AHP offers a robust framework for predicting and managing construction delays, providing valuable insights for improving project management practices. Future work should focus on expanding the dataset and refining the models to enhance their applicability across different regions and project types. © The Author(s), under exclusive licence to Springer Nature Switzerland AG 2024.
引用
收藏
页码:389 / 399
页数:10
相关论文
共 43 条
[1]  
Afolayan A., Ojokoh B., Adetunmbi A., Performance analysis of fuzzy analytic hierarchy process multi-criteria decision support models for contractor selection, Scientific African, 9, (2020)
[2]  
Aladayleh Jameel K., Gisbert F.P.S., Fuentes Bargues J.L., Factores influyentes en el retraso de los proyectos de construcción: Un estudio exploratorio en una universidad pública jordana, (2020)
[3]  
almahameed B.A., Bisharah M., Applying machine learning and particle swarm optimization for predictive modeling and cost optimization in construction project management, Asian Journal of Civil Engineering, 25, 2, pp. 1281-1294, (2024)
[4]  
Alsharef A., Banerjee S., Uddin S.J., Albert A., Jaselskis E., Early impacts of the COVID-19 pandemic on the United States construction industry, International Journal of Environmental Research and Public Health, 18, 4, (2021)
[5]  
Arabiat A., Al-Bdour H., Bisharah M., Predicting the construction projects time and cost overruns using K-nearest neighbor and artificial neural network: A case study from Jordan, Asian Journal of Civil Engineering, 24, 7, pp. 2405-2414, (2023)
[6]  
Asiedu R., Adaku E., Cost overruns of public sector construction projects: A developing country perspective, International Journal of Managing Projects in Business, 13, 1, pp. 66-84, (2019)
[7]  
Bekr G.A., Study and assessment of causes and effects of delay in large public construction projects in Jordan, International Journal of Applied Engineering Research, 13, 8, pp. 6204-6210, (2018)
[8]  
Berrar D., Cross-validation, Encyclopedia of Bioinformatics and Computational Biology, 542, (2019)
[9]  
Cevikbas M., Isik Z., An overarching review on Delay analyses in Construction projects, Buildings, 11, 3, (2021)
[10]  
Cooper D.F., Grey S., Raymond G., Walker P., Project Risk Management Guidelines, (2005)