Results of investigations into the erosion of blading have shown that the chief factors determining the intensity of erosion of the blading of turbines are the concentration of the abrasive particles and the velocity of the steam in the flow section. Corrosion is intensified by thermal cyclings during startup and shutdown of the units, which cause the scale to flake and to be carried into the turbine. Ways to combat erosion by reducing the allowable temperature of the walls of tubes of the superheating circuit, wider use of scale-resisting steels, such as austenitic steels instead of pearlitic outlet stages of superheaters and reheaters, are discussed.
引用
收藏
页码:77 / 79
相关论文
共 19 条
  • [1] WAYS OF PREVENTING EROSION OF BLADING IN FIRST STAGES OF HIGH-PRESSURE AND INTERMEDIATE PRESSURE CYLINDERS OF TURBINES OF POWER GENERATING UNITS
    SHKOLNIK, GT
    LUZHNOV, MI
    ZELENSKII, VG
    THERMAL ENGINEERING, 1972, 19 (06) : 77 - 79
  • [2] Comprehensive rotor service life study for high & intermediate pressure cylinders of high power steam turbines
    Peshko, V.
    Chernousenko, O.
    Nikulenkova, T.
    Nikulenkov, A.
    PROPULSION AND POWER RESEARCH, 2016, 5 (04) : 302 - 309
  • [4] DEVELOPMENT OF MEASURES TO IMPROVE THE RELIABILITY OF THE FLANGED JOINTS OF HIGH-PRESSURE HEATERS OF 800 MW POWER GENERATING UNITS.
    Nosul'ko, D.R.
    Bugasov, A.V.
    Thermal Engineering (English translation of Teploenergetika), 1987, 31 (11): : 635 - 637
  • [5] Ways toward updating the low-pressure cylinders for high-capacity turbines (a feasibility study)
    Lazarev L.Y.
    Sokolov V.S.
    Fadeev V.A.
    Chizhov V.V.
    Power Technology and Engineering, 2002, 36 (5) : 272 - 274
  • [6] High-Pressure Deaerator for 300-MW Power Generating Units
    Egorov P.V.
    Gimmel’berg A.S.
    Mikhailov V.G.
    Chuprakov M.V.
    Baeva A.N.
    Power Technology and Engineering, 2016, 50 (02) : 188 - 191
  • [7] Experience with Construction of High-pressure Centrifugal Fans for High-capacity Power Plant Units.
    Semov, V.V.
    Levinson, T.D.
    Lyamin, A.G.
    Energomashinostroenie, 1981, (07): : 8 - 11
  • [8] The Design Features of the High- and Intermediate-Pressure Cylinders with Forced Cooling for Turbines for Ultrasupercritical Steam Conditions
    Yu. K. Petrenya
    L. A. Khomenok
    I. I. Pichugin
    O. A. Vladimirskii
    V. M. Lyapunov
    A. S. Lisyanskii
    Yu. Ya. Kachuriner
    T. A. Ignat’eva
    S. A. Ivanov
    Thermal Engineering, 2008, 55 (1) : 39 - 44
  • [9] The design features of the high-and intermediate-pressure cylinders with forced cooling for turbines for ultrasupercritical steam conditions
    Petrenya, Yu.K.
    Khomenok, L.A.
    Pichugin, I.I.
    Vladimirskii, O.A.
    Lyapunov, V.M.
    Lisyanskii, A.S.
    Kachuriner, Yu.Ya.
    Ignat'Eva, T.A.
    Ivanov, S.A.
    Thermal Engineering, 2008, 55 (01) : 39 - 44
  • [10] EVALUATING CORROSIVITY OF MEDIUM IN CONDENSATE-FEED CIRCUIT OF HIGH-PRESSURE AND SUPERCRITICAL PRESSURE POWER GENERATING UNITS
    KLOCHKOV, VN
    THERMAL ENGINEERING, 1975, 22 (04) : 72 - 76