Layout of roadway under goaf based on scale effect of mining cross upper coal pillar

被引:0
|
作者
Lyu K. [1 ]
He F. [1 ,2 ]
Xu X. [1 ]
Wang F. [3 ]
Qin B. [1 ]
Li L. [1 ]
机构
[1] School of Energy and Mining, China University of Mining and Technology-Beijing, Beijing
[2] Beijing Key Laboratory for Precise Mining of Intergrown Energy and Resources, China University of Mining and Technology Beijing, Beijing
[3] Yanzishan Coal Mine, Jinneng Holding Group Co., Ltd., Datong
关键词
coal pillar system; contugous coal seam; mining cross the upper coal pillar; remaining coal pillar; roof; the deviatoric stress invariant; transverse translation layout;
D O I
10.13199/j.cnki.cst.2021-0610
中图分类号
学科分类号
摘要
With the condition of contugous double-thick coal seams downward mining as the background, in view of the adverse effects of upper remaining coal pillars on the stability of mining roadway and stope, the field measurement and theoretical analysis are adopted to study the regional characteristics of the deviatoric stress invariant under section coal pillar, the mechanism of strong strata behaviors during mining cross the upper boundary coal pillar and its scale effect. The research shows that: ① When the position of open-off cuts is not even in the upper seam, a transverse translation layout is adopted for the lower mining roadway, which not only place the roadway in a stable stress environment, but also prevent the collapse disaster by transform the whole mining cross the upper coal pillar into twice small-range processes. ② The stress state of floor rock under section coal pillar is analyzed with the second deviatoric stress invariant (J2) intensity,the third deviatoric stress invariant (J3) intensity,and the second deviatoric stress invariant (J2) horizontal gradient. The floor is partitioned by the three indexes, and the minimum horizontal distance between roadway and section coal pillar is determined to be 24 m. ③ During the mining cross the upper coal pillar, the combined interaction of the first or periodical weighting and the sudden instability of roof and coal pillar system is the basic reasons for the strong strata behaviors. Based on the scale effect of mining cross the upper coal pillar, the maximum horizontal distance between mining roadway and section coal pillar is determined to be 36 m. The feasibility and rationality of the transverse translation layout of 30 m in lower mining roadway was verified by the field measurement of typical coal mine. © 2023 Coal Science and Technology. All rights reserved.
引用
收藏
页码:52 / 60
页数:8
相关论文
共 24 条
  • [1] DAI Wenxiang, PAN Weidong, LI Meng, Et al., Study on layout and support technology of strongly disturbed roadway in contiguous coal seam[J], Coal Science and Technology, 48, 12, pp. 61-67, (2020)
  • [2] FU Xing, WANG Xin, SU Zhigang, Et al., Study on law of strata behavior in shallow-buried working face under contiguous gobs[J], Coal Science and Technology, 47, 7, pp. 149-155, (2019)
  • [3] ZHANG Baisheng, Research on surrounding rock control theory and technology of very close coal seam mining, (2008)
  • [4] ZHANG Baisheng, YANG Shuangsuo, KANG Lixun, Et al., Discussion on method for determining reasonable position of roadway for ultra-close multi-seam[J], Chinese Journal of Rock Mechanics and Engineering, 27, 1, (2008)
  • [5] XU Lei, ZHANG Hailiang, GENG Dongkun, Et al., Principal stress difference evolution in floor under pillar and roadway layout[J], Journal of Mining & Safety Engineering, 32, 3, pp. 478-484, (2015)
  • [6] JU Jinfeng, XU Jialin, ZHU Weibing, Et al., Mechanism of support crushing while mining out of upper goaf-side coal pillar in close distance seams of Shendong mining area[J], Chinese Journal of Rock Mechanics and Engineering, 32, 7, (2013)
  • [7] JU Jinfeng, XU Jialin, Influence of leading instability in the upper dip coal pillar boundary to the strong strata behaviors during the working face out of the pillar[J], Journal of China Coal Society, 37, 7, pp. 1080-1087, (2012)
  • [8] XU Jingmin, ZHU Weibing, JU Jinfeng, Mechanism of dynamic mine pressure occurring below adjacent upper chamber mining goaf with shallow cover depth[J], Journal of China Coal Society, 42, 2, pp. 500-509, (2017)
  • [9] SHEN Wenlong, BAI Jianbiao, ZHAO Zhiyong, Et al., Three indexes method for roadway layout below the closed residual bearing coal pillar[J], Journal of Mining & Safety Engineering, 35, 3, pp. 465-472, (2018)
  • [10] CHENG Hui, ZHAO Hongbao, XU Jianfeng, Et al., Study on floor heave mechanism and control technology of roadway based on slip line field theory[J], Journal of Mining Science and Technology, 6, 3, pp. 314-323, (2021)