A GA-based fuzzy optimal model for time-cost trade-off in a project with resources consideration

被引:0
|
作者
Parveen, Sultana [1 ]
Saha, Surajit Kumar [2 ]
机构
[1] Department of Industrial and Production Engineering, Bangladesh University of Engineering and Technology
[2] Titas Gas Transmission and Distribution Company Ltd., Dhaka-1215, 105, Kazi Nazrul Islam Avenue
关键词
Algorithm; CPM; Critical path method; Fuzzy set; Fuzzy time-resources trade-off; GA; Genetic algorithm; Multi-objective optimisation; TCTP; Time-cost trade-off problems;
D O I
10.1504/IJISE.2013.056094
中图分类号
学科分类号
摘要
The project managers' major concern is to complete project cost effectively and timely. But, in real life, the project completion time and cost may vary significantly as an effect of uncertainty such as weather, political and social disturbances, inflation, site congestion, human factors, productivity level, etc. Minimisation of project cost directly depends on proper utilisation of resources. Therefore, a GA-based fuzzy optimal model is proposed in this study incorporating multi-objective approach (MAWA) for project time-cost trade-off. In this study, fuzzy set theory is applied to model the managers' behaviour in predicting time and resources of activities and α-cut method in fuzzy logic theory is used as a measure of accepted risk level. In addition, the activities of project are crashed and penalty is induced for delay to make such problem realistic. The proposed model leads the managers to choose the Pareto optimal time-cost solutions under different risk levels as well as their associated degree of belief in a more flexible and realistic manner. Finally, this proposed model is used to solve a real problem. Copyright © 2013 Inderscience Enterprises Ltd.
引用
收藏
页码:153 / 170
页数:17
相关论文
共 50 条
  • [1] Modeling project time-cost trade-off in fuzzy random environment
    Ke, Hua
    Ma, Junjie
    APPLIED SOFT COMPUTING, 2014, 19 : 80 - 85
  • [2] A Fuzzy Random Time-Cost Trade-off Model
    Ke, Hua
    Ma, Weimin
    PROCEEDINGS OF THE EIGHTH INTERNATIONAL CONFERENCE ON INFORMATION AND MANAGEMENT SCIENCES, 2009, 8 : 633 - 637
  • [3] Optimization models and a GA-based algorithm for stochastic time-cost trade-off problem
    Ke, Hua
    Ma, Weimin
    Ni, Yaodong
    APPLIED MATHEMATICS AND COMPUTATION, 2009, 215 (01) : 308 - 313
  • [4] New fuzzy models for time-cost trade-off problem
    Ke, Hua
    Ma, Weimin
    Gao, Xin
    Xu, Weihua
    FUZZY OPTIMIZATION AND DECISION MAKING, 2010, 9 (02) : 219 - 231
  • [5] Time-cost trade-off analysis of project networks in fuzzy environments
    Chen, Shih-Pin
    Tsai, Ming-Jiun
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2011, 212 (02) : 386 - 397
  • [6] A time-cost trade-off model with resource consideration using genetic algorithm
    Chua, DKH
    Chan, WT
    Govindan, K
    CIVIL ENGINEERING SYSTEMS, 1997, 14 (04): : 291 - 311
  • [7] AN IMPROVED TIME-COST TRADE-OFF MODEL WITH OPTIMAL LABOR PRODUCTIVITY
    Lin, Chien-Liang
    Lai, Yu-Che
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2020, 26 (02) : 113 - 130
  • [8] New fuzzy models for time-cost trade-off problem
    Hua Ke
    Weimin Ma
    Xin Gao
    Weihua Xu
    Fuzzy Optimization and Decision Making, 2010, 9 : 219 - 231
  • [9] Fuzzy Multi-objective Programming Application for Time-Cost Trade-off of CPM in Project Management
    Yang, Gino K.
    COMPUTATIONAL COLLECTIVE INTELLIGENCE: TECHNOLOGIES AND APPLICATIONS, PT I, 2010, 6421 : 215 - 229
  • [10] Time-Cost Trade-off Problems of Engineering Project with Running Income
    Li, Hongxian
    Ouyang, Hongxiang
    2008 INTERNATIONAL CONFERENCE ON RISK MANAGEMENT AND ENGINEERING MANAGEMENT, ICRMEM 2008, PROCEEDINGS, 2008, : 9 - +