Effects of project's physical characteristics on cost deviation in road construction

被引:0
作者
Mahamid, Ibrahim [1 ]
机构
[1] Civil Engineering Department, Hail University, Hail
关键词
Cost deviation; Cost overrun; Dummy variables; Physical characteristics; Road construction;
D O I
10.1016/j.jksues.2012.04.001
中图分类号
学科分类号
摘要
This study is conducted to investigate the effect of projects’ physical characteristics on cost deviation in road construction using data from road construction projects awarded in the West Bank – Palestine over the years 2007–2010. The study is based on a sample of 74 road construction projects. Based on these data, regression models are developed. A questionnaire survey is also conducted to determine the impact of projects’ physical characteristics on cost deviation in road construction. The questionnaire survey included 14 owners, 30 contractors, and 25 consultants. The considered characteristics are: project size (i.e. small, medium, and large), estimated cost, road length, road width, terrain conditions, soil and rock suitability, and soil and rock drill ability. The results reveal that the average of cost deviation in road construction is 16.73%, ranging from −20.33% to 56.01%. The correlation between cost deviation in road construction projects and the above mentioned parameters is investigated. © 2012
引用
收藏
页码:81 / 88
页数:7
相关论文
共 50 条
[11]   Perceptions of stakeholders in project procurement for road construction [J].
Kornevs, Maksims ;
Hauge, Jannicke Baalsrud ;
Meijer, Sebastiaan .
COGENT BUSINESS & MANAGEMENT, 2018, 5 (01) :1-16
[12]   Do Longer Projects Have Larger Cost Deviation Than Shorter Construction Projects? [J].
Belay, Alemu Moges ;
Torp, Olav .
CREATIVE CONSTRUCTION CONFERENCE 2017, CCC 2017, 2017, 196 :262-269
[13]   Preliminary Cost Estimating for Road Construction Projects [J].
Mahamid, Ibrahim ;
Bruland, Amund .
PROCEEDINGS OF 2010 INTERNATIONAL CONFERENCE ON CONSTRUCTION AND REAL ESTATE MANAGEMENT, VOLS 1-3, 2010, :158-161
[14]   Genetic Algorithms for Construction Time-Cost-Quality Trade-Off: A Road Project Case Study [J].
Sorrentino, Mariarosa .
IN BO-RICERCHE E PROGETTI PER IL TERRITORIO LA CITTA E L ARCHITETTURA, 2013, 4 (02) :163-176
[15]   INTERNALIZATION OF THE COST OF ENVIRONMENTAL IMPACTS IN ROAD CONSTRUCTION PROJECTS [J].
Protopapas, Angelos L. ;
Stamatopoulou, Athanasia .
MANAGEMENT OF TECHNOLOGICAL CHANGES, VOL 1, 2009, :703-706
[16]   Physical Characterization of Granular Components Used in Road Construction [J].
Arias-Garcia, Pablo A. ;
Medici, Maria E. ;
Unac, Rodolfo O. ;
Vidales, Ana M. ;
Lizcano, Arcesio .
POWDERS AND GRAINS 2009, 2009, 1145 :163-+
[17]   A study and identification of the time and cost overrun in the construction project [J].
Chandragiri, Anand babu ;
Jeelani, Syed Hamim ;
Akthar, Salim ;
Lingeshwaran, N. .
MATERIALS TODAY-PROCEEDINGS, 2021, 47 :5426-5431
[18]   Conceptual Cost Estimate of Road Construction Projects in Saudi Arabia [J].
Mahamid, Ibrahim .
JORDAN JOURNAL OF CIVIL ENGINEERING, 2013, 7 (03) :285-294
[19]   Identification of Risk Factors Cause Cost Overrun at Toll Road Project [J].
Nurdiana, Asri ;
Susanti, Riza ;
Suwarto, Fardzanela .
ADVANCED SCIENCE LETTERS, 2018, 24 (12) :9534-9536
[20]   Environment, resources, and surroundings based dynamic project schedule model for the road construction industry in New Zealand [J].
Purushothaman, Mahesh Babu ;
Kumar, Sumit .
SMART AND SUSTAINABLE BUILT ENVIRONMENT, 2022, 11 (02) :294-312