Experience in Modernizing High-Pressure Heaters for Low-Power Turbine Units

被引:0
作者
Permyakov, K.V. [1 ]
Narevich, T.P. [1 ]
Emelyanov, E.V. [2 ]
机构
[1] JSC “NPO CKTI”, St. Petersburg
[2] LLC “TSK”, St. Petersburg
关键词
high-pressure heaters; low-power turbine units; modernization; operation data; replacement; testing results; thermal efficiency;
D O I
10.1007/s10749-024-01813-y
中图分类号
学科分类号
摘要
High-pressure heaters with stainless tubes were developed on the basis of previously tested technical solutions. These heaters replaced high-pressure heaters PV-150-3M with brass heat exchanger tubes in the regeneration system of the PR-12.9-2.8 (AP-25-2) turbine unit. Disadvantages of the replaced heaters, which caused their unsatisfactory thermal efficiency, thus complicating the operation of the regeneration system, are considered. The observed operational disadvantages are eliminated in the new heaters, which resulted in their higher thermal efficiency than that of the replaced ones, as confirmed by test and operation data. The example of heaters PV-150-3M demonstrates that high-pressure chamber heaters of low-power turbine units kept in operation for normal initial steam parameters can be successfully replaced with more advanced units. © Springer Science+Business Media, LLC, part of Springer Nature 2024.
引用
收藏
页码:305 / 309
页数:4
相关论文
共 5 条
[1]  
Tubyansky L.I., Frenkel L.D., Steam High-Pressure Turbines of Leningrad Metallurgical Plant, (1956)
[2]  
Information-Reference Catalog [in Russian, Heat-Exchange Equipment for Thermal and Nuclear Power Plants.
[3]  
Permyakov K.V., Experience of Reconstruction of Vertical Network Water Heaters Kept in Operation, ., No. 8,, pp. 42-47, (2013)
[4]  
Permyakov K.V., Experience in Increasing the Thermal Efficiency of Vertical Network Water Heaters at Their Reconstruction, No. 12, pp. 30-34, (2013)
[5]  
Permyakov V.A., Permyakov K.V., Koshelev S.M., New Vertical Network Water Heaters of PSVC Type for Boiler Houses, Chpps and Industrial Power Units, No. 12, pp. 13-17, (2003)