I’ve survived numerous stressful outages. So, let me share seven valuable tips. First, line up extra craftspeople that you can bring in if necessary. By this, I mean have boilermakers available from companies other than the one hired to do the turnaround, and arrange for additional scaffolders, electricians, etc. The foremen managing these extra troops shouldn’t come from your primary contractor. Your primary contractor’s foremen will be swamped meeting scheduled goals.