Solution models construction for open shop scheduling problem with setup, processing, and removal times separated

被引:2
作者
Low, Chinyao [1 ]
Yeh, Jinn-Yi [1 ]
Low, Fang-Wu [1 ]
机构
[1] Department of Industrial Engineering, Da-Yeh University, Da-Tsuen, Chang-hua
来源
Journal of the Chinese Institute of Industrial Engineers | 2003年 / 20卷 / 06期
关键词
Open shop scheduling; Removal; Setup; Simulated annealing; Total job tardiness;
D O I
10.1080/10170660309509261
中图分类号
学科分类号
摘要
In this research, we look the setup, processing, and removal times as separatable, then take the sequence-independent setup and dependent removal times into account when deal with an open shop scheduling problem with the objective to minimize the total job tardiness. The addressed problem is first described as a 0-1 integer programming model, and following, a simulated annealing based heuristic is proposed to get an near optimal schedule in a reasonable computation time. During the research, the parameters used in the heuristics that affect the solution quality and efficiency are analyzed and designed; then for the constructed heuristic, a good parameter setting is suggested. The experimental results are reported, and provided for the references for the further research.
引用
收藏
页码:565 / 574
页数:9
相关论文
共 50 条
  • [31] Optimization Solution to Lot Sizing and Scheduling Problem in Hybrid Flow-shop
    Song Fugen
    Lei Dayang
    2012 FIFTH INTERNATIONAL SYMPOSIUM ON COMPUTATIONAL INTELLIGENCE AND DESIGN (ISCID 2012), VOL 2, 2012, : 231 - 235
  • [32] Two-machine robotic cell scheduling problem with sequence-dependent setup times
    Zarandi, M. H. Fazel
    Mosadegh, H.
    Fattahi, M.
    COMPUTERS & OPERATIONS RESEARCH, 2013, 40 (05) : 1420 - 1434
  • [33] Hybrid Method for Solving Flexible Open Shop Scheduling Problem with Simulated Annealing Algorithm and Multi-agent Approach
    Witkowski, Tadeusz
    Antczak, Pawel
    Antczak, Arkadiusz
    MANUFACTURING SCIENCE AND TECHNOLOGY, PTS 1-8, 2012, 383-390 : 4612 - 4619
  • [34] Open shop scheduling problem with a multi-skills resource constraint: a genetic algorithm and an ant colony optimisation approach
    Ciro, Guillermo Campos
    Dugardin, Frederic
    Yalaoui, Farouk
    Kelly, Russell
    INTERNATIONAL JOURNAL OF PRODUCTION RESEARCH, 2016, 54 (16) : 4854 - 4881
  • [35] Polynomial time algorithms for special open shop problems with precedence constraints and unit processing times
    Brasel, H
    Kluge, D
    Werner, F
    RAIRO-RECHERCHE OPERATIONNELLE-OPERATIONS RESEARCH, 1996, 30 (01): : 65 - 79
  • [37] Using Improved Particle Swarm Optimization To Solve Open Shop Scheduling Problem With Two Criteria
    Ghadim, Mohammad Reza Kabarazad
    Bahrami, Behnam
    Bayat, Arash
    MATERIALS SCIENCE AND INFORMATION TECHNOLOGY, PTS 1-8, 2012, 433-440 : 4936 - 4941
  • [38] An effective hybrid simulated annealing and two mixed integer linear formulations for just-in-time open shop scheduling problem
    Seyed Hossein Hashemi Doulabi
    Milad Avazbeigi
    Sahar Arab
    Hamid Davoudpour
    The International Journal of Advanced Manufacturing Technology, 2012, 59 : 1143 - 1155
  • [39] An effective hybrid simulated annealing and two mixed integer linear formulations for just-in-time open shop scheduling problem
    Doulabi, Seyed Hossein Hashemi
    Avazbeigi, Milad
    Arab, Sahar
    Davoudpour, Hamid
    INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2012, 59 (9-12) : 1143 - 1155
  • [40] A 3/2 Algorithm for Two-Machine Open Shop with Route-Dependent Processing Times
    V. A. Strusevich
    A. J. A. van de Waart
    R. Dekker
    Journal of Heuristics, 1999, 5 : 5 - 28