Optimization on Stripping Plan of Outsourced Open-Pit Mines

被引:0
作者
Wang Q. [1 ]
Zhang Z.-T. [1 ]
Gu X.-W. [1 ]
Xu X.-C. [1 ]
机构
[1] School of Resources & Civil Engineering, Northeastern University, Shenyang
来源
Dongbei Daxue Xuebao/Journal of Northeastern University | 2018年 / 39卷 / 01期
关键词
Economic life; Equipment update; Feasible range of unit cost; Outsourcing; Stripping peak;
D O I
10.12068/j.issn.1005-3026.2018.01.025
中图分类号
学科分类号
摘要
Since the "stripping peak " has a negative effect on mine production, the tactics of equipment update and the optimization on stripping plan of outsourced open-pit mines were studied. Based on the relation between the cost of stripping equipment, the production capacity and the changing of the service age, a dynamic economic life model was established to decide the retire time of a single equipment. Meanwhile, the configuration algorithm steps of a specific equipment was also given out. First, a series of different levels of mine stripping and outsourced stripping boundaries were set to calculate the feasible range of unit cost for the outsourced program, then the outsourced contract price was determined in the feasible range; Finally, based on the contract price, the net present value of the total cost was analyzed to get the optimized outsourced plan. It is proved that the cost of reducing equipment investment by this method is higher than the cost of outsourced rock stripping. © 2018, Editorial Department of Journal of Northeastern University. All right reserved.
引用
收藏
页码:123 / 127
页数:4
相关论文
共 12 条
[1]  
Newman A.M., Rubio E., Caro R., Et al., A review of operations research in mine planning, Interfaces, 40, 3, pp. 222-245, (2010)
[2]  
Chen J.-Z., Optimization and regulation for stripping-ration of open-pits mines, (2001)
[3]  
Yun Q.-X., A new method to balance open-pit mine stripping work, Nonferrous Metals(Mining Section), 4, pp. 15-18, (1984)
[4]  
Zuo R., Optimization and regulation of open-pit stripping ratio, (2011)
[5]  
Alarie S., Gamache M., Overview of solution strategies used in truck dispatching systems for open pit mines, International Journal of Surface Mining, Reclamation and Environment, 16, 1, pp. 59-76, (2002)
[6]  
Ercelebi S.G., Bascetin A., Optimization of shovel-truck system for surface mining, Journal of the Southern African Institute of Mining and Metallurgy, 109, 7, pp. 433-439, (2009)
[7]  
Celebi N., An equipment selection and cost analysis system for open-pit coal mines, International Journal of Surface Mining Reclamation and Environment, 12, 4, pp. 181-187, (1998)
[8]  
Hartman J.C., Rogers J., Dynamic programming approaches for equipment replacement problems with continuous and discontinuous technological change, IMA Journal of Management Mathematics, 17, 2, pp. 26-30, (2006)
[9]  
Rogers J.L., Hartman J.C., Equipment replacement under continuous and discontinuous technological change, IMA Journal of Management Mathematics, 16, 1, pp. 23-36, (2005)
[10]  
Sevim H., Wang Q., De Tomi G., Economics of contracting overburden removal, Proceedings of the International Symposium APCOM, pp. 573-584, (1990)