Reasonable distance for super-large section neighborhood tunnel of granite residual soil with shallow-buried bias

被引:3
作者
Chen, Qiunan [1 ]
Zhao, Leijun [1 ]
Xie, Xiaoyu [1 ,2 ]
He, Chengbin [1 ]
Cao, Yunjiang [1 ]
机构
[1] School of Civil Engineering, Hunan University of Science and Technology, Xiangtan
[2] Hunan Road & Bridge Construction Group Corporation, Changsha
来源
Zhongnan Daxue Xuebao (Ziran Kexue Ban)/Journal of Central South University (Science and Technology) | 2015年 / 46卷 / 09期
基金
中国国家自然科学基金;
关键词
Granite residual soil; Large-span tunnels with small clear spacing in shallow buried; Numerical simulation; Optimization of construction method; Reasonable spacing;
D O I
10.11817/j.issn.1672-7207.2015.09.042
中图分类号
学科分类号
摘要
In order to discuss the relationship between reasonable spacing and degree of bias of granite residual soil shallow-buried bias tunnels with small spacing span, the bias ratio index P was introduced. After the tunnel portal of bias neighborhood tunnel models were built for three kinds of slope gradient, i. e. 1:7, 1:5 and 1:3, the impact of granite residual soil surrounding rock tunnel construction methods optimization and different rates of bias P on the reasonable minimum spacing were discussed based on the software FLAC3D. The results show that the double side heading tunnel construction method is more suitable for bias of 1.13, and that the minimum reasonable distance of tunnel is 24 m, the middle pillar is the weakest part, the settlement of pillar above the group is the largest, the axial forces of the supporting bolt of both sides of the tunnel are the largest, and during the construction process the plastic deformation of both sides near the pillar is also the biggest. The numerical simulation method is feasible and effective; therefore, the rock on the plate of rock pillar must be firstly consolidated during tunnel construction, and rock both in the middle and under the plate must be consolidated to ensure the stability of the middle rock pillars. © 2015, Central South University of Technology. All right reserved.
引用
收藏
页码:3475 / 3480
页数:5
相关论文
共 14 条
[1]  
Gong J., Xia C., Zhu H., Et al., Optimal analysis of construction schemes for Heshang small-space tunnels with large section, Rock and Soil Mechanics, 30, 1, pp. 236-240, (2009)
[2]  
Chen Q., Wang Q., Xie X., Et al., Mechanical characteristics of supporting structure for flat super-large section small spacing tunnels, Journal of Highway and Transportation Research and Development, 29, 9, pp. 89-94, (2012)
[3]  
Zhang H., Qiu W., Feng J., Mechanical performance of shared rock of neighborhood tunnels, Chinese Journal of Geotechnical Engineering, 32, 3, pp. 434-439, (2010)
[4]  
An Y., Shi S., Peng L., Et al., Construction behavior of double down-side drifts in a weak tunnel with shallow cover, Journal of Highway and Transportation Research and Development, 26, 1, pp. 114-119, (2009)
[5]  
Code for construction and acceptance of metro engineering
[6]  
Code for design of road tunnel
[7]  
Chen W., Zhu Z., Current situation and analysis of short-distance overlap tunnel, Modern Tunnelling Technique, 39, 1, pp. 42-47, (2002)
[8]  
Lo K.W., Chong L.K., Leung L.F., Et al., Field instrumentation of a multiple tunnels interaction problem, Tunnels and Tunnelling, 18, pp. 4-16, (1998)
[9]  
Japan Society of Civil Engineers(JSCE), Japanese Shield Tunnel Standard and Comment, pp. 209-214, (2011)
[10]  
Yamaguchi I., Yamazaki I., Kiritani Y., Study on ground-tunnel interactions of four shield tunnels driven in close proximity, in relation to design and construction of parallel shield tunnels, Tunnelling and Underground Space Technology, 13, 3, pp. 289-304, (1998)