Modelling open pit dynamics using discrete simulation

被引:16
|
作者
Askari-Nasab, H. [1 ]
Frimpong, S. [2 ]
Szymanski, J. [1 ]
机构
[1] School of Mining and Petroleum Engineering, University of Alberta, Edmonton, AB
[2] Department of Mining and Nuclear Engineering, University of Missouri-Rolla, Rolla, MO
关键词
Open pit mining; Stochastic simulation; Strategic and tactical mine planning;
D O I
10.1080/17480930600720206
中图分类号
学科分类号
摘要
The objective in any mining operation is to exploit ore at the lowest possible cost with the prospect of maximizing profits. The planning of an open pit mine is an economic exercise, constrained by certain geological, operating, technological and local field factors. Heuristic methods, economic parametric analysis, operations research and genetic algorithms have been used to formulate periodic open pit planning problems. Open pit design, optimization and subsequent materials scheduling problems are governed by stochastic dynamic process. Thus, current algorithms are limited in their abilities to address problems arising from these random and dynamic field processes. The primary objective of this study is to use a discrete stochastic simulation to capture the random field processes associated with open pit design and materials scheduling. An open pit production simulator (OPPS), implemented in MATLAB, based on a modified elliptical frustum is used to model the geometry of open pit layout expansion. The simulator mimics the periodic expansion of the open pit layouts. The interaction of the open pit expansion model with the geological and economic block model returns the respective amount of ore, waste, stockpile materials, and the net present value of the venture. A case study of an iron ore deposit with 114 000 blocks was carried out to verify and validate the model. The optimized pit limit was designed using the Lerchs - Grossman algorithm. The best-case annual schedule, generated by the shells node in Whittle Four-X, yielded a net present value (NPV) of $414 million over a 21-year mine life at a discount rate of 10% per annum. The best scenario out of 5000 simulation iterations using OPPS resulted in an NPV of $422 million over the same time span. Further research, based on hybrid stochastic simulation in conjunction with reinforcement learning, can provide a powerful tool for addressing the random field and dynamic processes in long-term open pit planning.
引用
收藏
页码:35 / 49
页数:14
相关论文
共 50 条
  • [1] Discrete event modelling and simulation in systems biology
    Ewald, R.
    Maus, C.
    Rolfs, A.
    Uhrmacher, A.
    JOURNAL OF SIMULATION, 2007, 1 (02) : 81 - 96
  • [2] An Approach to Locate an In Pit Crusher in Open Pit Mines
    Rahmanpour, M.
    Osanloo, M.
    Adibee, N.
    AkbarpourShirazi, M.
    INTERNATIONAL JOURNAL OF ENGINEERING, 2014, 27 (09): : 1475 - 1484
  • [3] Numerical Modelling Challenges in Rock Engineering with Special Consideration of Open Pit to Underground Mine Interaction
    Shapka-Fels, Tia
    Elmo, Davide
    GEOSCIENCES, 2022, 12 (05)
  • [4] Monitoring unstable slopes in an open pit lignite mine using ARIMA
    Ozsen, H.
    JOURNAL OF THE SOUTHERN AFRICAN INSTITUTE OF MINING AND METALLURGY, 2020, 120 (03) : 173 - 180
  • [5] Synthetic Rock Mass Modelling and Geotechnical Mapping: An Open Pit Mine Case Study in Anisotropic Rock
    Bester, M.
    Stacey, T. R.
    Russell, T.
    INTERNATIONAL JOURNAL OF MINING RECLAMATION AND ENVIRONMENT, 2021, 35 (05) : 356 - 378
  • [6] Application of ARENA Simulation Software for Evaluation of Open Pit Mining Transportation Systems - A Case Study
    Hashemi, Ali Saadatmand
    Sattarvand, Javad
    PROCEEDINGS OF THE 12TH INTERNATIONAL SYMPOSIUM CONTINUOUS SURFACE MINING - AACHEN 2014, 2015, : 213 - 224
  • [7] Enhancing Transportation Fleet Efficiency in Open-Pit Mining via Simulation: a Case Study
    Khajevand, Somaye
    Rezakhah, Mojtaba
    Monjezi, Masoud
    Manriquez, Fabian
    JOURNAL OF MINING AND ENVIRONMENT, 2025, 16 (03): : 997 - 1007
  • [8] Simulation of a large multiple pit mining operation using GPSS/H
    Stout, Clifford E.
    Conrad, Paul W.
    Todd, Charles S.
    Rosenthal, Scott
    Knudsen, H. Peter
    Conrad, P.W. (pconrad@mtech.edu), 1600, Inderscience Enterprises Ltd. (04): : 278 - 295
  • [9] Predicting open-pit mine production using machine learning techniques
    Kumah, Faustin N.
    Saim, Alex K.
    Oppong, Millicent N.
    Arthur, Clement K.
    JOURNAL OF SUSTAINABLE MINING, 2024, 23 (02): : 118 - 131
  • [10] Simulation Optimization of Shovel-Truck System in Open-Pit Mines Considering Rockmass Parameters
    Pathan, Shafi Muhammad
    Pathan, Abdul Ghani
    Memon, Muhammad Saad
    JOURNAL OF ADVANCED TRANSPORTATION, 2025, 2025 (01)