Development of a 3D geomechanical model test system for non-pillar mining with automatically formed roadway and its engineering application

被引:0
作者
Wang Q. [1 ,2 ,3 ]
Jiang B. [1 ,3 ]
Xin Z. [2 ,3 ]
He M. [1 ,3 ]
Li S. [2 ]
Zhang P. [2 ,3 ]
Wang Y. [2 ,3 ]
Jiang Z. [2 ,4 ]
机构
[1] State Key Laboratory for Geo-mechanics and Deep Underground Engineering, China University of Mining and Technology, Beijing
[2] Research Center of Geotechnical and Structural Engineering, Shandong University, Jinan, 250061, Shandong
[3] Research Institute of Deep Underground Science and Engineering, China University of Mining and Technology, Beijing
[4] Shandong Tianqin Engineering and Technology Limited Company, Heze, 274799, Shandong
来源
Yanshilixue Yu Gongcheng Xuebao/Chinese Journal of Rock Mechanics and Engineering | 2020年 / 39卷 / 08期
基金
中国国家自然科学基金;
关键词
Development of test system; Field application; Geomechanical model test; Mining engineering; N00; technology; Non-pillar mining technology with automatically formed roadway;
D O I
10.13722/j.cnki.jrme.2020.0084
中图分类号
学科分类号
摘要
The non-pillar mining technology of roof cutting and pressure releasing with automatically formed roadway(AFR) is a new type of coal mining method, which takes advantage of the mining pressure and rock mass expansion characteristic to automatically form roadways and hence, achieves coal mining without requiring excavating mining roadways and reserving protective coal pillars. In order to study the movement mechanism of overlying strata, the mining pressure behavior and failure mechanism of AFR in the whole mining process of the non-pillar mining with AFR, a 3D geomechanical model test system for non-pillar mining with AFR was independently developed, which composes of reaction and hydraulic loading subsystem, automatic mining and roadway forming subsystem and high-precision real-time monitoring subsystem. The model test system, equipped with a complete set of test devices to simulate the core techniques such as mining, roof pre-splitting and roadway automatic forming, can actually simulate the whole mining process of mining and forming roadway integration by the non-pillar mining technology of roof cutting and pressure releasing with AFR and monitor the mining pressure of whole working face. The geomechanical model tests with different model sizes in the range of 5.5 m in length, 2.4 m in height and 3.0 m in width can be carried out through a combined anti-force device. Taking the China's first working face of N00 technology-S1201-II working face of Ningtiaota Mine Coal as the engineering background, the 3D geomechanical model test was carried out by applying the model test system to study the most complicated N00 technology in non-pillar mining technologies with AFR. The mining pressure behavior of N00 technology was revealed and the control mechanism of the AFR surrounding rock was cleared. The key control positions of AFR were obtained, and the corresponding engineering suggestions were put forward to guide the following field application. The field monitoring results are basically consistent with the model test, which verifies the rationality and effectiveness of the model test system. © 2020, Science Press. All right reserved.
引用
收藏
页码:1582 / 1594
页数:12
相关论文
共 37 条
[1]  
QIAN Minggao, XU Jialin, WANG Jiachen, Further on the sustainable mining of coal, Journal of China Coal Society, 43, 1, pp. 1-13, (2018)
[2]  
HE Manchao, XIE Heping, PENG Suping, Et al., Study on rock mechanics in deep mining engineering, Chinese Journal of Rock Mechanics and Engineering, 24, 16, pp. 2803-2813, (2005)
[3]  
WANG Q, JIANG Z H, JIANG B, Et al., Research on an automatic roadway formation method in deep mining areas by roof cutting with high-strength bolt-grouting, International Journal of Rock Mechanics and Mining Sciences, 128, (2020)
[4]  
WANG Qi, QIN Qian, GAO Song, Et al., Relationship between rock drilling parameters and rock uniaxial compressive strength based on energy analysis, Journal of China Coal Society, 43, 5, pp. 1289-1295, (2018)
[5]  
WANG Qi, QIN Qian, XU Shuo, Et al., A testing method for rock c-φ parameter based on digital drilling test technology, Journal of China Coal Society, 44, 3, pp. 915-922, (2019)
[6]  
LIU Yang, SHI Pingwu, Existing problem on longwall remaining coal pillars support mining, Journal of China Coal Society, 32, 6, pp. 565-569, (2007)
[7]  
ISLAVATH S R, DEB D, KUMAR H., Numerical analysis of a longwall mining cycle and development of a composite longwall index, International Journal of Rock Mechanics and Mining Sciences, 89, pp. 43-54, (2016)
[8]  
WANG Q, JIANG B, PAN R, Et al., Failure mechanism of surrounding rock with high stress and confined concrete support system, International Journal of Rock Mechanics and Mining Sciences, 102, pp. 89-100, (2018)
[9]  
DOU Linming, HE Ye, ZHANG Weidong, Hazards of rock burst in island coal face and its control, Chinese Journal of Rock Mechanics and Engineering, 22, 11, pp. 1866-1869, (2003)
[10]  
WANG Qi, XU Shuo, JIANG Bei, Et al., Research Progress of Confined Concrete Support Theory and Technology for Underground Engineering, Journal of China Coal Society