Application of real-time monitoring technology to foundation settlement of sloping breakwaters in construction

被引:0
作者
Wang W. [1 ]
Xu K. [1 ]
Wang H.-L. [2 ]
Li L.-L. [2 ]
机构
[1] Department of Geotechnical Engineering, Nanjing Hydraulic Research Institute, Nanjing
[2] Dongying Port Construction Investment Co., Ltd., Dongying
来源
Yantu Gongcheng Xuebao/Chinese Journal of Geotechnical Engineering | 2017年 / 39卷
关键词
GPS; Real-time monitoring; Settlement; Settlement plate; Sloping breakwater;
D O I
10.11779/CJGE2017S1017
中图分类号
学科分类号
摘要
In recent years, China's port construction exhibits the development trend of large scale and deep water, and many ports are not the same type of seawall construction. Riprap construction of sloping breakwaters in open waters endures many complex factors from the external environment. Especially, coastal regions have distribution of deep and soft soil layers. With the increase in riprap amount and breakwater size, the real-time monitoring of settlement deformation is critical to control construction speed and project quality. According to the project situation and the characteristics of GPS technique, a real-time monitoring method for foundation settlement of sloping breakwater is proposed, including manufacture, laying and observation of subsidence monitoring equipments. The application of engineering example shows that the proposed method is suitable for the complex environment of riprap construction, and the settlement monitoring information can provide reliable basis for adjusting the intensity of riprap so as to ensure the safety of sloping breakwaters. © 2017, Editorial Office of Chinese Journal of Geotechnical Engineering. All right reserved.
引用
收藏
页码:85 / 90
页数:5
相关论文
共 8 条
[1]  
Han L.-A., Harbor engineering structure, (2008)
[2]  
Chen Y., Analysis of long-term settlement rule on breakwater project treated by blasting compaction, Port Engineering Technology, 50, 2, pp. 58-60, (2013)
[3]  
Dai P., Li X., Construction technology and quality control for sloping breakwater, China Water Transport, 14, 7, pp. 314-315, (2014)
[4]  
Su B., Settlement reservation control in construction of a deepwater breakwater, Construction Materials & Decoration, 12, pp. 292-293, (2015)
[5]  
Dong C.-Z., Huang F., Duan Y.-M., Application of GPS in engineering survey, Journal of Zhejiang University of Science and Technology, 16, 1, pp. 14-16, (2004)
[6]  
Zhang H.-P., Wen Y.-B., Zhang Z.-Y., Et al., Analysis of examples of GPS static surveying and RTK surveying, Bulletin of Surveying and Mapping, 1, pp. 28-31, (2006)
[7]  
Li Y.-H., Application of GPS orientation system in the survey construction of tunnels, Journal of Guang Dong Communications Polytechnic, 5, 3, pp. 45-47, (2006)
[8]  
Li Z.-H., GPS technology in the application of deformation monitoring, Gnss World of China, 26, 2, pp. 18-25, (2001)