Analyses of Pre-Excavation Grouting for TBM Tunnelling

被引:0
|
作者
Wannenmacher H. [1 ]
Schlicke M. [2 ]
机构
[1] Implenia Österreich GmbH., Tunnelling & Civil Engineering, Innsbrucker Bundesstraße 67, Salzburg
[2] Technical University of Munich, Chair of Construction Process Management, Arcisstrasse 21, München
来源
Geomechanik und Tunnelbau | 2023年 / 16卷 / 01期
关键词
Grouting; Mechanized tunneling; Pre-Excavation Grouting; Sealing; TBM; Tunnel; Unlined Tunnels; Utility tunnels; Water Inflow;
D O I
10.1002/geot.202200069
中图分类号
学科分类号
摘要
Pre-excavation grouting (PEG) is essential for mitigating groundwater inflow to unlined tunnel structures. Prevention of initial water inflow proved best practice to balance groundwater conditions throughout the utilisation of a tunnel. The grouted rock mass acts as a circumferential sealing barrier instead of a secondary lining to minimise groundwater inflow to an acceptable level over the structure's lifetime. The construction of unlined tunnels relies on existing favourable in-situ rock mass conditions with an overall low hydraulic head, mainly to keep the effort of grouting inferior and avoid an unbalanced proportion of pre-excavation grouting during the tunnel construction works. From the operational perspective of tunnelling works, pre-excavation grouting delineates the continuous excavation process of a TBM and represents a discontinuative work process. In addition, grouting includes an exploration process ahead of the cutterhead to predict the ground conditions to align the sealing demand of the rock mass. Generally, pre-excavation grouting foresees the drilling of mainly open boreholes with a considerable length of 20 m to 25 m ahead of the tunnel boring machine (TBM). Establishing a continuous grouted zone around the tunnel demands an overlapping of the grouting rings ranging from 2 m to 10 m. The overlapping decreases the excavation length of the TBM adequately. The repetitive grouting process interfering with the excavation consists of various processes such as exploration including water loss measuring (WLM), the drilling and grouting of boreholes and the hardening time. TBM tunnelling depends on the systematic and continuous implementation of construction procedures. Therefore, based on current static pre-excavation grouting, an agile combined grouting and excavation approach is presented, incorporating a reliable pre-excavation grouting, a systematic TBM excavation and a specific balance of long-term sealing and high utilisation rates for TBM excavation. © 2023, Ernst und Sohn. All rights reserved.
引用
收藏
页码:55 / 59
页数:4
相关论文
共 50 条
  • [31] Grouting to remove piles from a tunnelling machine cutter-head
    Liao, Hung-Jiun
    Cheng, Shih-Hao
    Wong, Ricky K. N.
    You, Chen-Fa
    Masaoka, Akihiro
    Hsieh, Cheng-Da
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-GEOTECHNICAL ENGINEERING, 2015, 168 (04) : 358 - 370
  • [32] Test of solidification characteristics of grouting and the effect on strata deformation in shield tunnelling
    Zhong, Xiaochun
    Qin, Weike
    Wang, Hai
    ADVANCED RESEARCH ON CIVIL ENGINEERING AND MATERIAL ENGINEERING, 2012, 568 : 80 - 84
  • [33] Geotechnical risk management approach for TBM tunnelling in squeezing ground conditions
    Swannell, Nicholas
    Palmer, Michael
    Barla, Giovanni
    Barla, Marco
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2016, 57 : 201 - 210
  • [34] Modelling of the EPB TBM shield tunnelling advance as a tool for geological characterization
    Culi, Laura
    Pujades, Estanislao
    Vazquez-Sune, Enric
    Jurado, Anna
    TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2016, 56 : 12 - 21
  • [35] A Mechanical Model of EPB-TBM Tunnelling in Mixed Face Strata
    Song, Tiantian
    Chen, Xiangsheng
    PROGRESS IN INDUSTRIAL AND CIVIL ENGINEERING, PTS. 1-5, 2012, 204-208 : 1472 - 1479
  • [36] The effect of variation in the strength of weathered Kowloon granite on slurry TBM tunnelling
    Shirlaw, James Nicholas
    Henderson, Thomas Oates
    Haryono, Ivan Stevanus
    Dudouit, Francois Claude Jean Marcel
    Salisbury, Christopher David
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-GEOTECHNICAL ENGINEERING, 2024,
  • [37] Dynamic characteristic analysis of TBM tunnelling in mixed-face conditions
    Zhang, Kaizhi
    Yu, Haidong
    Liu, Zhongpo
    Lai, Xinmin
    SIMULATION MODELLING PRACTICE AND THEORY, 2010, 18 (07) : 1019 - 1031
  • [38] Advances in Non-excavation Grouting Reinforcement Materials in the Road Engineering
    Zhang L.
    Wen P.
    Wang C.
    Di S.
    Yin W.
    Wang, Chaohui (wchh0205@163.com), 2017, Cailiao Daobaoshe/ Materials Review (31): : 98 - 105
  • [39] Effect of jet grouting and dewatering on an adjacent tunnel in a Shanghai deep excavation
    Wang, Li
    Zheng, Gang
    Ou, Ruonan
    PROCEEDINGS OF THE INSTITUTION OF CIVIL ENGINEERS-GROUND IMPROVEMENT, 2019, 172 (04) : 274 - 284
  • [40] Mechanical Analysis of Removable Blocks During TBM Tunnelling in Blocky Rock Masses in View of TBM-Block Interaction
    Wang, Shuaifeng
    Zhang, Zixin
    Huang, Xin
    PROCEEDINGS OF GEOSHANGHAI 2018 INTERNATIONAL CONFERENCE: ROCK MECHANICS AND ROCK ENGINEERING, 2018, : 346 - 351