Research on Influencing Factors and Control Measures of Construction Cost Overrun in China's Expressway Projects

被引:0
作者
Chen S. [1 ,2 ]
Fan X. [1 ]
Cai B. [1 ]
机构
[1] Fujian University of Technology, China
[2] Lulea University of Technology, Sweden
关键词
Construction cost overrun; DEMATEL; Expressway; ISM; SD;
D O I
10.4018/IJFSA.325067
中图分类号
学科分类号
摘要
In China, the expressways have been built a lot over the past decade. The construction of the expressway suffers from usual cost overrun. There are many factors of different stakeholders influencing the construction cost of expressways, and it is difficult to control all of them. Therefore, it is necessary to identify the key factors causing expressway construction cost overrun and take corresponding cost control measures. In this article, decision-making trial and evaluation laboratory (DEMATEL), interpretative structural modeling method (ISM) and system dynamics (SD) are integrated as DEMATEL-ISM-SD method to identify the key driving factors of expressway construction cost overrun and simulate the interactions of these factors to find the cost control measures. A case in China has been selected as an example to demonstrate how to use the proposed method. As a result, six key factors from different stakeholders are found. Then, six corresponding measures are put forward. This study can provide guidance for expressway construction cost control. © 2023 IGI Global. All rights reserved.
引用
收藏
相关论文
共 26 条
  • [1] Attri R., Dev N., Sharma V., Interpretive structural modelling (ISM) approach: An overview, Research Journal of Management Sciences, 2, 2, pp. 3-8, (2013)
  • [2] Chai H., Researches on reliability and validity of inspection procedure in questionnaire design, WORLD SCI-TECH R&D, 32, pp. 548-550, (2010)
  • [3] Chen J., Li Y., Luan Qi, Research on the overall risk evaluation model of investment project, Project Management Technology, 9, 1, pp. 27-32, (2011)
  • [4] Feng H., Zhang J., Li W., Research on risk assessment of highway construction cost in east Africa based on hierarchy-fuzzy comprehensive evaluation method, Science & Technology for Development, 16, 5, pp. 532-542, (2020)
  • [5] Hsu C. W., Kuo T. C., Chen S. H., Hu A. H., Using DEMATEL to develop a carbon management model of supplier selection in green supply chain management, Journal of Cleaner Production, 56, pp. 164-172, (2013)
  • [6] Huang Y., Analysis of factors influencing the cost of expressway projects, Construction Economy, pp. 128-130, (2011)
  • [7] Huang Y., Hu S., Yao S., System dynamics analysis and safety risk of building tower crane, Journal of Safety and Environment, 20, pp. 2060-2068, (2020)
  • [8] Lei S., Gao W., Analysis of cost influencing factors and discussion on control methods of expressway engineering projects, HIGHWAY, pp. 140-143, (2010)
  • [9] Mathew S. A., Tran D. Q., Nguyen P. H., Evaluation of cost growth factors in design-build highway projects using structural equation modeling, American Society of Civil Engineers, 147, 7, (2021)
  • [10] 2021 Nationl Toll Road Statistal Bulletin, (2021)