The need for multi-LOD 4D simulations in construction projects

被引:0
|
作者
Butkovic B. [1 ]
Heesom D. [1 ]
Oloke D. [1 ]
机构
[1] Faculty of Science and Engineering, University of Wolverhampton
来源
Journal of Information Technology in Construction | 2019年 / 24卷
关键词
4D; BIM; Level of Detail (LOD); Simulation;
D O I
10.36680/j.itcon.2019.014
中图分类号
学科分类号
摘要
The increasing application of BIM processes and technologies has facilitated an increase in the use of 4D (3D+Time) simulations of construction projects. Previous research has acknowledged the benefit of 4D models in the project planning and construction phases enhancing communication between construction teams and avoiding unforeseen conflicts during the build process. The development of BIM has spurred a deeper understanding of the issues surrounding Level of Development, Level of Information (LOI) and Level of Detail (LOD) pertaining to the graphical detail and non-graphical information of the static geometric design model. However, to date there is limited research thoroughly investigating the issue of LOD within 4D applications. This work presents an ongoing study to derive a framework for the development of more dynamic 4D simulations incorporating discrete forms of LOD. Level of graphical detail (LODg) corresponds to the graphical detail of the model geometry and also the 'granularity' of the geometry required for dynamic 4D production, whilst the temporal level of detail (LODti) relates to time period required between state changes in the model during the simulation. In order to support the development of the framework, an industry-based survey was conducted to assess the application of 4D, subsequent issues and use cases around levels of graphical and temporal details to improve dynamic 4D simulations. The work concludes with the development of a framework and schematic to support the specification of the LOD of a 4D simulation (LOD4d) throughout the various phases of a construction project. © 2019 The author(s). This is an open access article distributed under the terms of the Creative Commons Attribution 4.0 International (https://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
引用
收藏
页码:256 / 272
页数:16
相关论文
共 47 条
  • [21] Application of 4D BIM Simulations for Safety and Schedule Integration of a Reconstruction Project for Oxygen Plant in Steel Works in Korea
    Kim, Chae-Yeon
    Lee, Jae-Sung
    Roh, Ho-Young
    Lee, Eul-Bum
    CIGOS 2021, EMERGING TECHNOLOGIES AND APPLICATIONS FOR GREEN INFRASTRUCTURE, 2022, 203 : 1487 - 1494
  • [22] Enhancing Construction Management Education through 4D BIM and VR: Insights and Recommendations
    Abouelkhier, Narmin
    Shafiq, Muhammad Tariq
    Rauf, Abdul
    Alsheikh, Negmeldin
    BUILDINGS, 2024, 14 (10)
  • [23] A quantitative analysis on the feasibility of 4D Planning Graphic Systems versus Conventional Systems in building projects
    Candelario-Garrido, Alonso
    Garcia-Sanz-Calcedo, Justo
    Reyes Rodriguez, Antonio Manuel
    SUSTAINABLE CITIES AND SOCIETY, 2017, 35 : 378 - 384
  • [24] Plane-based registration of construction laser scans with 3D/4D building models
    Bosche, Frederic
    ADVANCED ENGINEERING INFORMATICS, 2012, 26 (01) : 90 - 102
  • [25] 4D-based automation of heavy lift planning in industrial construction projects
    Han, SangHyeok
    Lei, Zhen
    Hermann, Ulrich
    Bouferguene, Ahmed
    Al-Hussein, Mohamed
    CANADIAN JOURNAL OF CIVIL ENGINEERING, 2021, 48 (09) : 1115 - 1129
  • [26] Applicability of 4D modeling for resource allocation in mega liquefied natural gas plant construction
    Zhou, Ying
    Ding, Lieyun
    Wang, Xiangyu
    Truijens, Martijn
    Luo, Hanbin
    AUTOMATION IN CONSTRUCTION, 2015, 50 : 50 - 63
  • [27] Development and validation of a framework for preventing and mitigating construction delay using 4D BIM platform in Bangladeshi construction sector
    Assafi, Mohammad Nafe
    Hossain, Md Mehrab
    Chileshe, Nicholas
    Datta, Shuvo Dip
    CONSTRUCTION INNOVATION-ENGLAND, 2023, 23 (05): : 1255 - 1278
  • [28] The evaluation and justification of the effectiveness of 4D CAD using multi-criteria analysis
    Reizgevicius, Marius
    Ustinovichius, Leonas
    Simanaviciene, Ruta
    Rasiulis, Romas
    Peliksa, Mykolas
    JOURNAL OF CIVIL ENGINEERING AND MANAGEMENT, 2014, 20 (06) : 884 - 892
  • [29] Increasing production efficiency through the reduction of transportation activities and time using 4D BIM simulations
    Perez, Cristina Toca
    Bastos Costa, Dayana
    ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2021, 28 (08) : 2222 - 2247
  • [30] Construction Progress Monitoring through the Integration of 4D BIM and SLAM-Based Mapping Devices
    Vassena, Giorgio P. M.
    Perfetti, Luca
    Comai, Sara
    Ventura, Silvia Mastrolembo
    Ciribini, Angelo L. C.
    BUILDINGS, 2023, 13 (10)