The need for multi-LOD 4D simulations in construction projects

被引:0
|
作者
Butkovic B. [1 ]
Heesom D. [1 ]
Oloke D. [1 ]
机构
[1] Faculty of Science and Engineering, University of Wolverhampton
来源
Journal of Information Technology in Construction | 2019年 / 24卷
关键词
4D; BIM; Level of Detail (LOD); Simulation;
D O I
10.36680/j.itcon.2019.014
中图分类号
学科分类号
摘要
The increasing application of BIM processes and technologies has facilitated an increase in the use of 4D (3D+Time) simulations of construction projects. Previous research has acknowledged the benefit of 4D models in the project planning and construction phases enhancing communication between construction teams and avoiding unforeseen conflicts during the build process. The development of BIM has spurred a deeper understanding of the issues surrounding Level of Development, Level of Information (LOI) and Level of Detail (LOD) pertaining to the graphical detail and non-graphical information of the static geometric design model. However, to date there is limited research thoroughly investigating the issue of LOD within 4D applications. This work presents an ongoing study to derive a framework for the development of more dynamic 4D simulations incorporating discrete forms of LOD. Level of graphical detail (LODg) corresponds to the graphical detail of the model geometry and also the 'granularity' of the geometry required for dynamic 4D production, whilst the temporal level of detail (LODti) relates to time period required between state changes in the model during the simulation. In order to support the development of the framework, an industry-based survey was conducted to assess the application of 4D, subsequent issues and use cases around levels of graphical and temporal details to improve dynamic 4D simulations. The work concludes with the development of a framework and schematic to support the specification of the LOD of a 4D simulation (LOD4d) throughout the various phases of a construction project. © 2019 The author(s). This is an open access article distributed under the terms of the Creative Commons Attribution 4.0 International (https://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, distribution, and reproduction in any medium, provided the original work is properly cited.
引用
收藏
页码:256 / 272
页数:16
相关论文
共 46 条
  • [1] THE NEED FOR MULTI-LOD 4D SIMULATIONS IN CONSTRUCTION PROJECTS
    Butkovic, Bogdan
    Heesom, David
    Oloke, David
    JOURNAL OF INFORMATION TECHNOLOGY IN CONSTRUCTION, 2019, 24 : 256 - 272
  • [2] 4D BIM Simulation Guideline for Construction Visualization and Analysis of Renovation Projects: A Case Study
    Alzarrad, M. Ammar
    Moynihan, Gary P.
    Parajuli, Aakash
    Mehra, Mayuri
    FRONTIERS IN BUILT ENVIRONMENT, 2021, 7
  • [3] Development of a 4D object-based system for visualizing the risk information of construction projects
    Kang, Leen Seok
    Kim, Sung-Keun
    Moon, Hyoun Seok
    Kim, Hyeon Seung
    AUTOMATION IN CONSTRUCTION, 2013, 31 : 186 - 203
  • [4] Modeling construction equipment in 4D simulation
    Amrollahibuki, R.
    Hammad, A.
    EWORK AND EBUSINESS IN ARCHITECTURE, ENGINEERING AND CONSTRUCTION, 2018, : 243 - 250
  • [5] 4D BIM for Construction Logistics Management
    Whitlock, Kane
    Abanda, Fonbeyin Henry
    Manjia, Marcelline Blanche
    Pettang, Chrispin
    Nkeng, George Elambo
    CIVILENG, 2021, 2 (02): : 325 - 348
  • [6] Evaluation of 4D BIM tools applicability in construction planning efficiency
    Martins, Savio Santana
    Jorge Evangelista, Ana Catarina
    Hammad, Ahmed W. A.
    Tam, Vivian W. Y.
    Haddad, Assed
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2022, 22 (15) : 2987 - 3000
  • [7] ANALYSIS OF MODERN SOFTWARE FOR VIRTUAL CONSTRUCTION (4D MODELING)
    Pimenov, S. I.
    RUSSIAN JOURNAL OF BUILDING CONSTRUCTION AND ARCHITECTURE, 2023, (03): : 61 - 72
  • [8] Investigating the Human Errors in 4D BIM Construction Scheduling
    Kandregula, Shravan Kumar
    Le, Tuyen
    CONSTRUCTION RESEARCH CONGRESS 2020: PROJECT MANAGEMENT AND CONTROLS, MATERIALS, AND CONTRACTS, 2020, : 750 - 757
  • [9] Monitoring Construction Progress Based on 4D BIM Technology
    Chen, Jingjing
    Wu, Juan
    Qu, Yan
    6TH INTERNATIONAL CONFERENCE ON ENVIRONMENTAL SCIENCE AND CIVIL ENGINEERING, 2020, 455
  • [10] Operative 4D planning and controlling for the digital construction site (OPS4D)
    Breit, M.
    Haeubi, F.
    Koenig, M.
    EWORK AND EBUSINESS IN ARCHITECTURE, ENGINEERING AND CONSTRUCTION, 2012, : 259 - 262