Cost Estimation of Metro Construction Projects Using Interpretable Machine Learning

被引:0
|
作者
Meng, Chuncheng [1 ]
Qu, Daoyuan [2 ]
Duan, Xiaochen [1 ]
机构
[1] Shijiazhuang Tiedao Univ, Sch Management, 17 Beierhuan East Rd, Shijiazhuang 050043, Peoples R China
[2] Shijiazhuang Tiedao Univ, Shijiazhuang 050043, Peoples R China
基金
中国国家自然科学基金;
关键词
Metro construction projects; Cost estimation; Interpretable machine learning; Light gradient boosting machine (LightGBM); Shapley additive explanations (SHAP); REGRESSION-ANALYSIS; MODEL; OPTIMIZATION;
D O I
10.1061/JCCEE5.CPENG-6018
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
The metro, renowned as an environmentally friendly mode of transportation due to its low energy consumption and minimal pollution, plays a crucial role in achieving sustainable urban growth. Due to the scarcity of information in the early stages of metro construction projects and the subjectivity of cost estimation (which relies heavily on the estimator's experience), it is always difficult to guarantee the accuracy of metro construction project cost estimation. Furthermore, the existing methodological models commonly used for cost estimation do not adequately consider the interpretability of the estimation results, making it difficult to promote their application in real-world scenarios. In this paper, an interpretable machine learning method is introduced into the study of cost estimation of metro construction projects, and a maximum relevance and minimum redundancy (mRMR)-light gradient boosting machine (LightGBM)-Shapley additive explanations (SHAP) interpretable assisted investment decision-making framework is proposed. The results show that the negative impact of variable multicollinearity on model prediction is avoided by quantitatively identifying the key driving variables of costing through mRMR based on the historical data of metro construction projects and macroeconomic data. LightGBM is employed to predict the cost of metro construction projects with a mean absolute percentage error of 13.00%, surpassing the accuracy of the five baseline models. The SHAP method's introduction explains the influence of key driving variables on the model prediction response at both global and local levels, which improves the decision trust of the cost estimation of metro construction projects. The study takes into account the impact of key driving variables on the model's prediction response in a real-world context and balances the needs for estimation accuracy and variable interpretability in real-world scenarios. In this study, we propose a new interpretable machine learning method that helps improve the decision trust of cost estimation for metro construction projects. We use the mRMR module to identify the key driving variables for cost. Based on the LightGBM module, we accurately fit the nonlinear relationship between the cost of metro construction projects and the key variables. The SHAP algorithm is introduced to analyze the effects of the key driving variables on the prediction of the model at both global and local levels. The combined mRMR-LightGBM-SHAP model is proven to have better prediction accuracy than the traditional prediction model under the same conditions, and the SHAP response results prove the reliability of the model prediction. The study also found that the inclusion of economic environment variables plays a positive role in improving the accuracy of cost estimation for metro construction projects. The research results can be mainly used by metro investment units to quickly confirm or review the cost of metro construction projects, and they can also help government departments pay close attention to the impact of the external economic environment on the cost of metro construction.
引用
收藏
页数:14
相关论文
共 50 条
  • [1] Predicting Cost Impacts of Nonconformances in Construction Projects Using Interpretable Machine Learning
    Koc, Kerim
    Budayan, Cenk
    Ekmekcioglu, Omer
    Tokdemir, Onur Behzat
    JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2024, 150 (01)
  • [2] Cost Estimation of Civil Construction Projects using Machine Learning Paradigm
    Arage, Sphurti S.
    Dharwadkar, Nagaraj V.
    2017 INTERNATIONAL CONFERENCE ON I-SMAC (IOT IN SOCIAL, MOBILE, ANALYTICS AND CLOUD) (I-SMAC), 2017, : 594 - 599
  • [3] Cost estimation and prediction in construction projects: a systematic review on machine learning techniques
    Tayefeh Hashemi, Sanaz
    Ebadati, Omid Mahdi
    Kaur, Harleen
    SN APPLIED SCIENCES, 2020, 2 (10):
  • [4] Cost estimation and prediction in construction projects: a systematic review on machine learning techniques
    Sanaz Tayefeh Hashemi
    Omid Mahdi Ebadati
    Harleen Kaur
    SN Applied Sciences, 2020, 2
  • [5] A taxonomy of machine learning techniques for construction cost estimation
    Karadimos, Panagiotis
    Anthopoulos, Leonidas
    INNOVATIVE INFRASTRUCTURE SOLUTIONS, 2024, 9 (11)
  • [6] Construction cost estimation of reinforced and prestressed concrete bridges using machine learning
    Kovacevic, Miljan
    Ivanisevic, Nenad
    Petronijevic, Predrag
    Despotovic, Vladimir
    GRADEVINAR, 2021, 73 (01): : 1 - 13
  • [7] Cost Estimation Model Using Modified Parameters for Construction Projects
    Ji, Sae-Hyun
    Ahn, Joseph
    Lee, Hyun-Soo
    Han, Kyeongjin
    ADVANCES IN CIVIL ENGINEERING, 2019, 2019
  • [8] Cost estimation methodology using database layer in construction projects
    Han, Kyeong Jin
    Lee, Hyun-Soo
    Park, Moonseo
    Ji, Sae-Hyun
    25TH INTERNATIONAL SYMPOSIUM ON AUTOMATION AND ROBOTICS IN CONSTRUCTION - ISARC-2008, 2008, : 470 - 475
  • [9] Improving cost estimation in construction projects
    Sayed, Mohamed
    Abdel-Hamid, Mohamed
    El-Dash, Karim
    INTERNATIONAL JOURNAL OF CONSTRUCTION MANAGEMENT, 2023, 23 (01) : 135 - 143
  • [10] Risk-Based Completion Cost Overrun Ratio Estimation in Construction Projects Using Machine Learning Classification Algorithms: A Case Study
    Turkyilmaz, Aynur Hurriyet
    Polat, Gul
    BUILDINGS, 2024, 14 (11)