Development of Risk Quantification Models in Road Infrastructure Projects

被引:6
作者
Senic, Aleksandar [1 ]
Dobrodolac, Momcilo [2 ]
Stojadinovic, Zoran [1 ]
机构
[1] Univ Belgrade, Fac Civil Engn, Belgrade 11000, Serbia
[2] Univ Belgrade, Fac Transport & Traff Engn, Belgrade 11000, Serbia
关键词
road infrastructure; risk prevention; risk management; extension of time; increasing contract price; SCHEDULE RISK; CONSTRUCTION; FUZZY; COMPLEXITY; COSTS;
D O I
10.3390/su16177694
中图分类号
X [环境科学、安全科学];
学科分类号
08 ; 0830 ;
摘要
Road infrastructure is a significant factor in the development of any country, affecting economic growth, social development, and environmental sustainability. Large infrastructure projects often face significant risks and uncertainties, which can lead to delays, budget over-runs, and an insufficient quality of the completed work. These issues undermine the economic viability of projects and affect the overall efficiency of infrastructure development. For these reasons, based on a literature review and completed project analysis, the risks that lead to an increasing Contract Price (ICP) and an Extension of Time (EoT) for the construction of the project are identified. Based on the results of the completed project analysis, the values of the ICP and EoT were quantified. Also, the probability of the occurrence of each risk in new projects was calculated. Based on the obtained results, a model was defined that groups risks into clusters. Risks in the first cluster should have priority for funding, and preventive measures are defined for them. The model obtained in this way can greatly enhance project management in real-world conditions and can lead to a significant reduction in project time and budget over-runs.
引用
收藏
页数:20
相关论文
共 55 条
  • [1] Acampa G., 2019, AIP C P
  • [2] A review of artificial intelligence based risk assessment methods for capturing complexity-risk interdependencies Cost overrun in construction projects
    Afzal, Farman
    Shao Yunfei
    Nazir, Mubasher
    Bhatti, Saad Mahmood
    [J]. INTERNATIONAL JOURNAL OF MANAGING PROJECTS IN BUSINESS, 2021, 14 (02) : 300 - 328
  • [3] Analysis of cost and schedule performance of international development projects
    Ahsan, Kamrul
    Gunawan, Indra
    [J]. INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2010, 28 (01) : 68 - 78
  • [4] Allahi F., 2017, P WORLD C ENG, P385
  • [5] Causes of delay in large construction projects
    Construction Engineering and Management Department, King Fahd University of Petroleum and Minerals, Box # 680, Dhahran, 31261, Saudi Arabia
    [J]. Int. J. Proj. Manage., 2006, 4 (349-357): : 349 - 357
  • [6] Modeling the Vibratory Compaction Process for Roads
    Bratu, Polidor
    Tonciu, Oana
    Nitu, Marilena Cristina
    [J]. BUILDINGS, 2023, 13 (11)
  • [7] Chan D. W. M., 1997, International Journal of Project Management, V15, P55, DOI 10.1016/S0263-7863(96)00039-7
  • [8] Evaluation of the eco-friendly crushed waste oyster shell mortars containing supplementary cementitious materials
    Chen, Da
    Zhang, Pengcheng
    Pan, Tao
    Liao, Yingdi
    Zhao, Hui
    [J]. JOURNAL OF CLEANER PRODUCTION, 2019, 237
  • [9] Validation of an Instrument to Measure Governance and Performance on Collaborative Infrastructure Projects
    Chen, Le
    Manley, Karen
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2014, 140 (05)
  • [10] The coefficient of determination R-squared is more informative than SMAPE, MAE, MAPE, MSE and RMSE in regression analysis evaluation
    Chicco, Davide
    Warrens, Matthijs J.
    Jurman, Giuseppe
    [J]. PEERJ COMPUTER SCIENCE, 2021,