Research on Construction Risk Assessment of Long-Span Cantilever Casting Concrete Arch Bridges Based on Triangular Fuzzy Theory and Bayesian Networks

被引:0
作者
He, Zhengyi [1 ]
Xiang, Yi [1 ]
Li, Linshu [1 ]
Wei, Mei [2 ]
Liu, Bonan [1 ]
Wu, Shuyao [1 ]
机构
[1] Hunan City Univ, Sch Civil Engn, Yiyang 413000, Peoples R China
[2] Hunan Art & Crafts Vocat Coll, Sch Digital Arts, Yiyang 413000, Peoples R China
关键词
construction risk assessment; cantilever casting concrete arch bridges; triangular fuzzy number; Bayesian network;
D O I
10.3390/buildings14092627
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Considering the complex construction processes involved, there are significant risks during the construction of long-span cantilever casting arch bridges. In this study, a risk assessment method for the construction process of cantilever casting concrete arch bridges was developed. The compositional elements and characteristics of safety risks in the construction of cantilever casting concrete arch bridges were clarified, and a safety risk source list that includes seven major risk sources and thirty-three minor risk sources was formed. Then, a Bayesian model for the risk analysis of cantilever casting concrete arch bridge construction was established, and a method was proposed to determine the prior and posterior probabilities of the Bayesian network using triangular fuzzy numbers. This method fully utilizes the experience of experts while avoiding the subjectivity of expert opinions. A cantilever casting concrete open spandrel arch bridge (Bridge A) with a total span length of 287 m was taken as an example, and a safety risk assessment was conducted during its construction process. The calculation results show that the construction safety risk level of Bridge A was level III. This engineering application verified the feasibility of determining key node parameters of the Bayesian network using triangular fuzzy numbers.
引用
收藏
页数:15
相关论文
共 27 条
  • [1] Exposure knowledge impact on regional seismic risk assessment of bridge portfolios
    Abarca, Andres
    Monteiro, Ricardo
    O'Reilly, Gerard J.
    [J]. BULLETIN OF EARTHQUAKE ENGINEERING, 2022, 20 (13) : 7137 - 7159
  • [2] Sustainable Risk Assessment through the Analysis of Financial Losses from Third-Party Damage in Bridge Construction
    Ahn, Sungjin
    Kim, Taehui
    Kim, Ji-Myong
    [J]. SUSTAINABILITY, 2020, 12 (08)
  • [3] [安朗 An Lang], 2015, [公路交通科技, Journal of Highway and Transportation Research and Development], V32, P91
  • [4] Andric J, 2014, EURODYN, P3073
  • [5] Bao L., 2012, J. Shenyang Jianzhu Univ. Nat. Sci, V28, P94
  • [6] Multi-Objective Risk Analysis and Documents Assessment of Bridge Construction Based on AHP-GRAY
    Bao, Longsheng
    Wang, Wenbiao
    Liu, Ketong
    Yu, Ling
    Niu, Hong
    [J]. ADVANCED SCIENCE LETTERS, 2011, 4 (6-7) : 2543 - 2546
  • [7] Chen J., 2023, J. Xian Shiyou Univ. (Nat. Sci.), V38, P127
  • [8] Probabilistic risk assessment for the construction phases of a PSC box girder railway bridge system with six sigma methodology
    Cho, Taejun
    Lee, Jeong-Bae
    Kim, Seong-Soo
    [J]. KSCE JOURNAL OF CIVIL ENGINEERING, 2011, 15 (01) : 119 - 130
  • [9] Construction Project Risk Assessment Using Existing Database and Project-Specific Information
    Choi, Hyun-Ho
    Mahadevan, Sankaran
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2008, 134 (11) : 894 - 903
  • [10] Discussion on the Measurements in Cantilever Construction with Guyed Hanging Basket
    Gui, Fangru
    [J]. ADVANCES IN CIVIL AND INDUSTRIAL ENGINEERING IV, 2014, 580-583 : 2797 - 2800