Lessons Learned from Construction Site Layout Planning Practices

被引:1
作者
Hansen, Seng [1 ]
机构
[1] Univ Agung Podomoro, Jakarta, Indonesia
来源
INGENIERIA E INVESTIGACION | 2024年 / 44卷 / 01期
关键词
construction site; empirical case study; Indonesia; project planning; POST-PROJECT REVIEWS; MANAGEMENT; SAFETY; MODEL; GIS;
D O I
10.15446/ing.investig.107160
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Proper layout planning is necessary to prepare a site for construction activities, prevent potential delays, and ensure project safety and security. Despite the considerable amount of studies regarding construction site layout planning, most research has relied on fabricated data using simulations, while, in fact, site layout is unique for each construction project, and its planning requires previous experience. This paper presents an in-depth study on site layout planning practices, as observed in four actual project cases. Using an empirical case study approach, these practices are collected through site observations, document examinations, and semi- structured interviews. Several discussions related to site layout planning practices are described, including the considerations, types, tasks and benefits related to proper site layout planning. The contribution of this paper is the ability to capture some lessons learned regarding construction site layout planning from actual project cases, which can be utilized by other parties for the benefit of future projects. The lessons learned allow developing appropriate strategies required by construction project teams in order to increase their response capability and hence be able to pro-actively make decisions regarding proper site layout planning.
引用
收藏
页数:11
相关论文
共 68 条
  • [1] Abdel-Fattah A., 2013, Doctoral thesis
  • [2] Adhika H. D., 2017, Jurnal Teknik ITS, V6, pC22
  • [3] A simulation-based approach for material yard laydown planning
    Alanjari, Pejman
    Razavialavi, Seyedreza
    AbouRizk, Simaan
    [J]. AUTOMATION IN CONSTRUCTION, 2014, 40 : 1 - 8
  • [4] Post-project reviews as a key project management competence
    Anbari, Frank T.
    Carayannis, Elias G.
    Voetsch, Robert James
    [J]. TECHNOVATION, 2008, 28 (10) : 633 - 643
  • [5] Dynamic site layout planning through minimization of total potential energy
    Andayesh, Mohsen
    Sadeghpour, Farnaz
    [J]. AUTOMATION IN CONSTRUCTION, 2013, 31 : 92 - 102
  • [6] Baroncini M., 2022, Lessons learnt in construction projects
  • [7] Binhomaid O. S., 2019, Doctoral thesis
  • [8] Identification of Effective Management Practices and Technologies for Lessons Learned Programs in the Construction Industry
    Caldas, Carlos H.
    Gibson, G. Edward, Jr.
    Weerasooriya, Runi
    Yohe, Angela M.
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2009, 135 (06): : 531 - 539
  • [9] ArcSite: Enhanced GIS for construction site layout
    Cheng, MY
    OConnor, JT
    [J]. JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1996, 122 (04): : 329 - 336
  • [10] Benchmarking initiatives in the construction industry:: Lessons learned and improvement opportunities
    Costa, Dayana B.
    Formoso, Carlos T.
    Kagioglou, Michail
    Alarcon, Luis F.
    Caldas, Carlos H.
    [J]. JOURNAL OF MANAGEMENT IN ENGINEERING, 2006, 22 (04) : 158 - 167