Cost and time risk factors in construction projects in the Dominican Republic

被引:0
作者
Fernandez-Valderrama, Pedro [1 ]
Urena-Estrella, Crismal [1 ]
Moyano, Juan [1 ]
Bienvenido-Huertas, David [2 ]
机构
[1] Univ Seville, Dept Graph Express & Bldg Engn, Seville, Spain
[2] Univ Granada, Dept Bldg Construct, Granada, Spain
关键词
construction; cost; developing country; risk assessment; time; OVERRUNS; DELAY;
D O I
10.3389/fbuil.2024.1307572
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
The building sector is very dynamic and complex, so construction works are surrounded by uncertainties. The deficiencies of this sector are mainly related to poor project planning and management, resulting in losses because of missed deadlines, cost overruns, reworks, and unsatisfied clients. For a project to be successful, all the parties involved should work together to effectively manage the risks that could emerge in the project life cycle. This research defines and establishes a classification of the factors causing cost and time deviations in construction projects in the Dominican Republic. For this purpose, the most common factors are compiled, and their risk levels are determined by using the data obtained in a survey in which professionals from the building sector participated. The indexes marked by the participants show that the serious risk factors are design variations and the variations made by clients, a tight project schedule and the preparation of bid offers, deficiencies in the work planning and schedule, the lack of skilled labour, and work performance errors.
引用
收藏
页数:15
相关论文
共 72 条
[1]  
Acharya Nimal Kumar, 2006, [Korean Journal of Construction Engineering and Management, 한국건설관리학회 논문집], V7, P177
[2]  
Ahmed S. M., 2003, Proceedings of the 39th annual ASC conference, P66
[3]   Factors affecting contractors' risk of cost overburden [J].
Akinci, B ;
Fischer, M .
JOURNAL OF MANAGEMENT IN ENGINEERING, 1998, 14 (01) :67-76
[4]   A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates [J].
Al Hosani, Ihsan Issa Ahmad ;
Dweiri, Fikri T. ;
Ojiako, Udechukwu .
INTERNATIONAL JOURNAL OF SYSTEM ASSURANCE ENGINEERING AND MANAGEMENT, 2020, 11 (06) :1250-1259
[5]   Delay and Cost Overrun in Infrastructure Projects in Jordan [J].
Al-Hazim, Nabil ;
Abu Salem, Zaydoun ;
Ahmad, Hesham .
7TH INTERNATIONAL CONFERENCE ON ENGINEERING, PROJECT, AND PRODUCTION MANAGEMENT, 2017, 182 :18-24
[6]  
Al-Momani A.H., 2000, INT J PROJ MANAG, V18, P51, DOI DOI 10.1016/S0263-7863(98)00060-X
[7]   Modified Mamdani-fuzzy inference system for predicting the cost overrun of construction projects [J].
Al-Nahhas, Yaman Saeid ;
Hadidi, Laith A. ;
Islam, Muhammad Saiful ;
Skitmore, Martin ;
Abunada, Ziyad .
APPLIED SOFT COMPUTING, 2024, 151
[8]   The significant factors causing delay of building construction projects in Malaysia [J].
Alaghbari, Wa'el ;
Kadir, Mohd. Razali A. ;
Salim, Azizah ;
Ernawati .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2007, 14 (02) :192-+
[9]  
Ameh OJ, 2010, J CONSTR DEV CTRIES, V15, P49
[10]   Appropriate budget contingency determination for construction projects: State-of-the-art [J].
Ammar, Taher ;
Abdel-Monem, Mohamed ;
El-Dash, Karim .
ALEXANDRIA ENGINEERING JOURNAL, 2023, 78 :88-103