External quality assurance of cost estimates in major public projects: empirical evidence on cost performance

被引:0
|
作者
Berg, Helene [1 ,2 ]
Nyhus, Ole Henning [3 ]
机构
[1] Norwegian Def Res Estab, Dept Strateg Anal, Kjeller, Norway
[2] Norwegian Univ Sci & Technol, Dept Civil & Environm Engn, Trondheim, Norway
[3] Norwegian Univ Sci & Technol, Trondheim, Norway
关键词
Cost performance; Cost overrun; Public sector; Learning effects; Project cost management; FRONT-END; FRAMEWORK; MANAGEMENT; GOVERNANCE;
D O I
10.1108/IJMPB-12-2023-0276
中图分类号
F [经济];
学科分类号
02 ;
摘要
PurposeValue creation for society from public projects requires that the overall benefits exceed the use of taxpayers' money. At the same time, cost overruns in public projects are a well-documented feature in the literature, but practical guidance on reducing the extent and magnitude of overruns is rare. In 2000, Norway introduced a governance regime that includes mandatory external quality assurance (QA) of cost estimates for major public projects. This paper compares the cost performance of public projects on each side of this QA scheme.Design/methodology/approachWe use an original dataset covering 1,704 projects from 2000 to 2021, reported first-hand from Norwegian public agencies. We apply quantitative methods in the form of descriptive statistics, regression models, and statistical testing of hypotheses to answer our research questions.FindingsThe mean cost overrun across projects in our dataset is smaller than several previous international studies have reported. We find no statistical support for different cost performances between QA and non-QA projects. Secondly, cost overruns seem to vary between different public sectors. A third finding is a small development with lower cost overruns over time for the non-QA projects, and we raise the question of whether the QA scheme has contributed to overall learning effects. The fourth finding is that cost deviations are quite independent of project size.Originality/valueThe paper offers novel insights for decision-makers and researchers on the effects of external quality assurance on cost performance in public projects.
引用
收藏
页码:455 / 475
页数:21
相关论文
共 50 条
  • [41] Managing Major Cost-Overrun Risks in Construction Projects in China
    Wang Jiayuan
    Zou, X. W.
    PROCEEDINGS OF CRIOCM 2008 INTERNATIONAL RESEARCH SYMPOSIUM ON ADVANCES OF CONSTRUCTION MANAGEMENT AND REAL ESTATE, 2008, : 238 - 243
  • [42] A hybrid forecasting model to predict the duration and cost performance of projects with Bayesian Networks
    Unsal-Altuncan, Izel
    Vanhoucke, Mario
    EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2024, 315 (02) : 511 - 527
  • [43] Time and Cost Performance of Costruction Projects in Southern and Cenrtal Regions of Penisular Malaysia
    Rahman, Ismail Abdul
    Memon, Aftab Hameed
    Nagapan, Sasitharan
    Latif, Qadir Bux Alias Imran
    Azis, Ade Asmi Abdul
    2012 IEEE COLLOQUIUM ON HUMANITIES, SCIENCE & ENGINEERING RESEARCH (CHUSER 2012), 2012,
  • [44] Quantitative appraisal of cost and time performance of construction projects in public and private universities in Osun State, Nigeria
    Olatunde N.A.
    Alao O.O.
    Olatunde, Nathaniel Ayinde (nathaniel.olatunde@uniben.edu), 1600, Emerald Group Holdings Ltd. (15): : 619 - 634
  • [45] An Empirical Investigation of Key Pre-project Planning Practices Affecting the Cost Performance of Green Building Projects
    Son, H.
    Lee, S.
    Kim, C.
    DEFINING THE FUTURE OF SUSTAINABILITY AND RESILIENCE IN DESIGN, ENGINEERING AND CONSTRUCTION, 2015, 118 : 37 - 41
  • [46] Estimating the cost effects of purchasing centralization-Empirical evidence from framework agreements in the public sector
    Karjalainen, K.
    JOURNAL OF PURCHASING AND SUPPLY MANAGEMENT, 2011, 17 (02) : 87 - 97
  • [47] Relationships between internal and external information systems integration, cost and quality performance, and firm profitability
    Maiga, Adam S.
    Nilsson, Anders
    Ax, Christian
    INTERNATIONAL JOURNAL OF PRODUCTION ECONOMICS, 2015, 169 : 422 - 434
  • [48] Modelling construction completion cost in Ghana public sector building projects
    Coffie G.H.
    Aigbavboa C.O.
    Thwala W.D.
    Asian Journal of Civil Engineering, 2019, 20 (7) : 1063 - 1070
  • [49] The cost performance of transportation projects: The fallacy of the Planning Fallacy account
    Love, Peter E. D.
    Sing, Michael C. P.
    Ika, Lavagnon A.
    Newton, Sidney
    TRANSPORTATION RESEARCH PART A-POLICY AND PRACTICE, 2019, 122 : 1 - 20
  • [50] An empirical study on a single company's cost estimations of 338 software projects
    Schuerhoff, Christian
    Hanenberg, Stefan
    Gruhn, Volker
    EMPIRICAL SOFTWARE ENGINEERING, 2023, 28 (01)