Efficient Project Scheduling with Autonomous Learning Opportunities

被引:0
作者
Hill, Alessandro [1 ]
Vossen, Thomas W. M. [2 ]
机构
[1] Univ Bologna, Dept Elect Elect & Informat Engn Guglielmo Marcon, I-40126 Bologna, Italy
[2] Univ Colorado, Leeds Sch Business, Boulder, CO 80309 USA
关键词
project management; scheduling; autonomous learning; TIME; MANAGEMENT; EXTENSIONS; VARIANTS; COST;
D O I
10.1287/ijoc.2023.0107
中图分类号
TP39 [计算机的应用];
学科分类号
081203 ; 0835 ;
摘要
We consider novel project scheduling problems in which the experience gained from completing selected activities can be used to accelerate subsequent activities. Given a set of potential learning opportunities, our model aims to identify the opportunities that result in a maximum reduction of the project makespan when scheduled in sequence. Accounting for the impact of such learning opportunities causes significant complications, due to the cyclic nature of the learning relations and their interference with the precedence network. We propose additive and subtractive algorithms that iteratively reschedule the project using an enhanced topological sorting algorithm. Learning opportunities are integrated, activated, and potentially deactivated in each step by maintaining the acyclicity of the combined precedence and learning network. To illustrate the challenges that arise in this setting, we first consider the special case where activities can learn from at most one other activity. Subsequently, we extend our approach to the general case that admits multiple learning opportunities. We show that our approaches guarantee the construction of an optimal solution in polynomial time. In a computational study using 340 small and large resource -unconstrained PSPlib instances, we analyze the model behavior under various scenarios of learning intensity and learning opportunity. We demonstrate that significant project speedups can be obtained when proactively accounting for learning opportunities.
引用
收藏
页码:761 / 783
页数:24
相关论文
共 34 条
[1]  
Ahuja R.K., 1993, NETWORK FLOWS THEORY
[2]   On the strength of time-indexed formulations for the resource-constrained project scheduling problem [J].
Artigues, Christian .
OPERATIONS RESEARCH LETTERS, 2017, 45 (02) :154-159
[3]   Project management with time, cost, and quality considerations [J].
Babu, AJG ;
Suresh, N .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1996, 88 (02) :320-327
[4]   Flow shop learning effect scheduling problem with release dates [J].
Bai, Danyu ;
Tang, Mengqian ;
Zhang, Zhi-Hai ;
Santibanez-Gonzalez, Ernesto D. R. .
OMEGA-INTERNATIONAL JOURNAL OF MANAGEMENT SCIENCE, 2018, 78 :21-38
[5]   A state-of-the-art review on scheduling with learning effects [J].
Biskup, Dirk .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 2008, 188 (02) :315-329
[6]   Optimal Intraproject Learning [J].
Cao, Huan ;
Hall, Nicholas G. ;
Wan, Guohua ;
Zhao, Wenhui .
M&SOM-MANUFACTURING & SERVICE OPERATIONS MANAGEMENT, 2024, 26 (02) :681-700
[7]   The multi-mode resource-constrained project scheduling problem with generalized precedence relations [J].
De Reyck, B ;
Herroelen, W .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1999, 119 (02) :538-556
[8]   Audit scheduling with overlapping activities and sequence-dependent setup costs [J].
Dodin, B ;
Elimam, AA .
EUROPEAN JOURNAL OF OPERATIONAL RESEARCH, 1997, 97 (01) :22-33
[9]  
Ebbinghaus Hermann., 1885, Uber das Gedachtnis. Untersuchungen zur experimentellen Psychologie
[10]   THE ANALYSIS OF ACTIVITY NETWORKS UNDER GENERALIZED PRECEDENCE RELATIONS (GPRS) [J].
ELMAGHRABY, SE ;
KAMBUROWSKI, J .
MANAGEMENT SCIENCE, 1992, 38 (09) :1245-1263