Rockburst prediction and early warning for a highway tunnel excavated by TBM based on microseismic monitoring

被引:0
作者
Zhao, Jian [1 ]
Huang, Dan [1 ]
Cai, Yongshun [1 ]
Huang, Dengxia [2 ]
Zhou, Xiaolong [2 ]
Wang, Fei [3 ]
Pan, Yuxiang [4 ]
机构
[1] BGRIMM Technol Grp, Inst Min Engn, Beijing, Peoples R China
[2] China Commun Construct Grp Co Ltd, China First Highway Engn Co Ltd, Beijing, Peoples R China
[3] Northeastern Univ, Key Lab, Minist Educ Safe Min Deep Met Mines, Shenyang, Peoples R China
[4] TU Bergakademie Freiberg, Geotech Inst, Freiberg, Germany
关键词
rockburst prediction; microseismic monitoring; cloud service platform; rockburst risk level; prediction criteria; HYDROPOWER STATION; RADIATED ENERGY; PROSPECTS; MECHANISM; LOCATION; LONG;
D O I
10.3389/feart.2024.1391509
中图分类号
P [天文学、地球科学];
学科分类号
07 ;
摘要
A newly developed microseismic (MS) monitoring system was employed in the Tianshan-Shengli tunnel to detect MS activities and then predict and provide early warning of rockburst disasters. The system not only has the advantages of accuracy of artificial analysis but also real-time analysis and warnings. The positioning accuracy for MS events is approximately 5-10 m. A new sensor installation scheme was proposed to achieve fast sensor installation and recovery, taking advantage of semicircular steel tubes and hose clamps. In addition, the rockburst risk level prediction criteria adopted multiple evaluation indexes such as MS event energy and moment magnitude and number, and it revealed that the evolution of maximum energy has a good positive correlation with that of maximum moment magnitude through analyzing the monitored MS events. It also showed that the rockburst generally occurred 2 days after the rock mass was exposed by the tunnel boring machine (TBM) tail shield and belonged to the delayed rockburst category, according to the field statistical results. The preliminary application cases indicated that the rockburst prediction and early warning based on MS monitoring agree with the site survey results. Therefore, the new MS monitoring system is a reliable tool for predicting and providing early warnings of rockburst disasters.
引用
收藏
页数:14
相关论文
共 52 条
[1]  
Arshad, 2016, ELECTRON J GEOTECH E, V21, P4459
[2]  
Barton N., 1974, ROCK MECH, V6, P189, DOI [DOI 10.1007/BF01239496, 10.1007/BF01239496]
[3]  
BOATWRIGHT J, 1984, B SEISMOL SOC AM, V74, P361
[4]   FLAC/PFC coupled numerical simulation of AE in large-scale underground excavations [J].
Cai, M. ;
Kaiser, P. K. ;
Morioka, H. ;
Minami, M. ;
Maejima, T. ;
Tasaka, Y. ;
Kurose, H. .
INTERNATIONAL JOURNAL OF ROCK MECHANICS AND MINING SCIENCES, 2007, 44 (04) :550-564
[5]   A fuzzy comprehensive evaluation methodology for rock burst forecasting using microseismic monitoring [J].
Cai, Wu ;
Dou, Linming ;
Zhang, Min ;
Cao, Wenzhuo ;
Shi, Ji-Quan ;
Feng, Longfei .
TUNNELLING AND UNDERGROUND SPACE TECHNOLOGY, 2018, 80 :232-245
[6]  
Cao AY, 2009, Min. Sci. Technol, V19, P718, DOI DOI 10.1016/S1674-5264(09)60131-9
[7]  
Chen BR, 2020, ROCK SOIL MECH, V41, P2422, DOI 10.16285/j.rsm.2019.1062
[8]   Research on the Law of Large-Scale Deformation and Failure of Soft Rock Based on Microseismic Monitoring [J].
Chen, Feng ;
Ma, Tianhui ;
Tang, Chun'an ;
Du, Yanhong ;
Li, Zhichao ;
Liu, Fei .
ADVANCES IN CIVIL ENGINEERING, 2018, 2018
[9]   Research Developments and Prospects on Microseismic Source Location in Mines [J].
Cheng, Jiulong ;
Song, Guangdong ;
Sun, Xiaoyun ;
Wen, Laifu ;
Li, Fei .
ENGINEERING, 2018, 4 (05) :653-660
[10]  
Cheon D.-S., 2008, Tunn. Undergr. Sp