Ultimate water level and deformation failures of the artificial dam in the coal mine underground reservoir

被引:1
|
作者
Kong, Xiang-song [1 ]
Yang, Wei [1 ]
Shan, Ren-liang [1 ]
Wang, Shuan [1 ]
Fang, Jie [2 ]
机构
[1] China Univ Min & Technol Beijing, Sch Mech & Civil Engn, Beijing 100083, Peoples R China
[2] China Energy Investment Corp Ltd, State Key Lab Water Resource Protect & Utilizat Co, Beijing 100011, Peoples R China
基金
中国国家自然科学基金;
关键词
Coal mine underground reservoir; Artificial dam; Ultimate water level; Similar simulation test; Numerical simulation;
D O I
10.1016/j.engfailanal.2024.108367
中图分类号
TH [机械、仪表工业];
学科分类号
0802 ;
摘要
Coal mine underground reservoirs provide a new choice for the protection and utilization of water resources. This paper takes the underground reservoir of Wulanmulun Mine as the background, and takes the MB-1 # artificial dam in the goaf of 31104 - 31116 working face of 3 - 1 coal seam as the research object. The theoretical model of artificial dam is established by elastic - plastic twoway slab theory, and the theoretical mechanical analysis and calculation are carried out. A similitude physical model for the coal mine underground reservoir was built by using the selfdeveloped nested dual-dynamic-pressure similitude simulation testing system. Later, the mechanical response and deformation failure features of the artificial dam under different water pressure values were analyzed and the ultimate water pressure was determined. In addition, FLAC3D was used to determine the stress-seepage field-coupling model for the artificial dam. Using this model, the influence of water pressure on the multi-load coupling effect of the artificial dam and coal pillar dam was characterized. The dam form is optimized and the safety water level evaluation method of the dam body is proposed. The research results are as follows: (1) Based on the theory of elastic - plastic two-way slab, the theoretical analysis model of artificial dam is established, the expression of the ultimate water level function of artificial dam is derived, and the theoretical ultimate water head is determined to be 18.2 m (2) The seepage law of underground reservoir under different water pressures is obtained, and the ultimate water pressure of the model is determined to be 11.43 kPa. (3) It is clarified that the failure modes of the artificial dam are seepage failure and mechanical failure, and it is revealed that the groove area is the weakest position where the dam is most vulnerable to failure. In view of the failure modes of the dam, the I-shaped structure artificial dam is proposed. (4) A safe water level assessment method is proposed for the constructed artificial dam. According to the analysis of on-site monitoring data of MB-1 # dam, the actual water level in the reservoir is within the allowable water level range of the artificial dam, and the whole reservoir is in a stable and relatively safe state at present. The reliability of this assessment method has been verified.
引用
收藏
页数:26
相关论文
共 50 条
  • [1] Seismic performance analysis of flat artificial dam of underground reservoir in coal mine
    Chi M.
    Li P.
    Cao Z.
    Wu Y.
    Zhang Y.
    Li H.
    Wu B.
    Meitan Xuebao/Journal of the China Coal Society, 2023, 48 (03): : 1179 - 1191
  • [2] Critical Instability and Dynamic Loading Laws of the Artificial Dam in the Coal Mine Underground Reservoir
    Xu, Chao
    Li, Xinpeng
    Wang, Kai
    Wang, Wenhua
    Guo, Lin
    Xu, Nuo
    JOURNAL OF ENERGY ENGINEERING, 2025, 151 (02)
  • [3] Stability analysis of mine underground reservoir artificial dam in Lijiahao Mine
    Bai D.-Y.
    Ju J.-F.
    Xu J.-L.
    Li J.-H.
    Meitan Xuebao/Journal of the China Coal Society, 2017, 42 (07): : 1839 - 1845
  • [4] Stability analysis of artificial dam in coal mine underground water reservoir based on the hydro-mechanical damage model
    Ma, Junpeng
    Zhang, Guangchao
    Zhou, Guanglei
    Zhang, Yong
    Meng, Xiangjun
    Zhao, Yongqiang
    Chen, Miao
    GEOMATICS NATURAL HAZARDS & RISK, 2023, 14 (01)
  • [5] Structural optimization of artificial dam body in coal mine underground reservoir based on orthotropic plate model
    Fang Z.
    Ju J.
    Cao Z.
    Wang X.
    Xu J.
    Ju, Jinfeng (jjfcumt@163.com), 1600, China Coal Society (45): : 1375 - 1384
  • [6] Design of Cutting Depth of Artificial Dam of Underground Reservoir in Wulanmulun Mine
    Kong, Xiang-song
    Fang, Jie
    Xu, Zhuang-zhuang
    Wang, Shuan
    Liu, Shuai
    2019 INTERNATIONAL CONFERENCE ON ADVANCES IN CIVIL ENGINEERING, ENERGY RESOURCES AND ENVIRONMENT ENGINEERING, 2019, 330
  • [7] Experimental study of mechanical properties of artificial dam for coal mine underground reservoir under cyclic loading and unloading
    Lyu, Xin
    Yang, Ke
    Xu, Chaoshui
    Fang, Juejing
    Duan, Minke
    Zhang, Zhainan
    GEOMECHANICS AND GEOPHYSICS FOR GEO-ENERGY AND GEO-RESOURCES, 2024, 10 (01)
  • [8] Investigation on groove depth of artificial dam of underground reservoir in coal mines
    Kong, Xiang-song
    Xu, Zhuang-zhuang
    Shan, Ren-liang
    Liu, Shuai
    Xiao, Sheng-chao
    ENVIRONMENTAL EARTH SCIENCES, 2021, 80 (06)
  • [9] Investigation on groove depth of artificial dam of underground reservoir in coal mines
    Xiang-song Kong
    Zhuang-zhuang Xu
    Ren-liang Shan
    Shuai Liu
    Sheng-chao Xiao
    Environmental Earth Sciences, 2021, 80
  • [10] Study on the Interaction Mechanism between Residual Coal and Mine Water in Goaf of Coal Mine Underground Reservoir
    Jiang, Binbin
    Zhao, Ze
    Liu, Deqian
    Cao, Zhiguo
    Tang, Jiawei
    Wu, Min
    Zhang, Haiqin
    Li, Peng
    Liang, Dingcheng
    SUSTAINABILITY, 2023, 15 (20)