BIM-based schedule generation and optimization using genetic algorithms

被引:9
作者
Wefki, Hossam [1 ]
Elnahla, Mohamed [1 ]
Elbeltagi, Emad [2 ,3 ]
机构
[1] Port Said Univ, Fac Engn, Civil Engn Dept, Port Said 42526, Egypt
[2] Qassim Univ, Coll Engn, Dept Civil Engn, Buraydah 51452, Saudi Arabia
[3] Mansoura Univ, Fac Engn, Struct Engn Dept, Mansoura 35516, Egypt
关键词
Building information modeling (BIM); Automation; Genetic algorithm; Automatic Scheduling; Construction; Optimization; Integrated project delivery (IPD); 5D simulation; 4D CAD; CONSTRUCTION; MANAGEMENT; SYSTEM;
D O I
10.1016/j.autcon.2024.105476
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This research presents a transformative framework to tackle challenges within the construction industry, where efficiency is hindered by limited digitalization and disjointed project phases. The framework seamlessly integrates state-of-the-art technologies, such as Building Information Modeling (BIM), Genetic Algorithms (GAs) for schedule optimization, 5D simulation, and a Business Intelligence (BI) Dashboard. By doing so, it effectively enhances productivity while bridging the gap between the realms of management and engineering. A comprehensive literature review underpins the framework's design, focusing mainly on BIM-based schedule generation and optimization. The approach's validity is demonstrated through a compelling case study, showcasing automated BIM model creation, BIM-Based schedule generation limited to structural elements of bottom-up Cast-insitu construction method, GAs-driven schedule optimization, 5D project simulation, and the integration of the BI dashboard. This research propels operational efficiency and promotes harmonious integration with pre-existing software systems, thus facilitating smoother adoption and adaptation.
引用
收藏
页数:22
相关论文
共 49 条
[11]   Automation in construction scheduling: a review of the literature [J].
Faghihi, Vahid ;
Nejat, Ali ;
Reinschmidt, Kenneth F. ;
Kang, Julian H. .
INTERNATIONAL JOURNAL OF ADVANCED MANUFACTURING TECHNOLOGY, 2015, 81 (9-12) :1845-1856
[12]   Scheduling with computer-interpretable construction method models [J].
Fischer, MA ;
Aalami, F .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 1996, 122 (04) :337-347
[13]  
Jaehyun P., 2015, COMPUT CIV ENG, P620, DOI DOI 10.1061/9780784479247.077
[14]   A method for planning of work-flow by combined use of location-based scheduling and 4D CAD [J].
Jongeling, Rogier ;
Olofsson, Thomas .
AUTOMATION IN CONSTRUCTION, 2007, 16 (02) :189-198
[15]   Improved link system between schedule data and 3D object in 4D CAD system by using WBS code [J].
Kang, Leen-Seok ;
Moon, Hyoun-Seok ;
Park, Seo-Young ;
Kim, Chang-Hak ;
Lee, Tai Sik .
KSCE JOURNAL OF CIVIL ENGINEERING, 2010, 14 (06) :803-814
[16]   Automated generation of construction plans from primitive geometries [J].
Kataoka, Makoto .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2008, 134 (08) :592-600
[17]   Generating construction schedules through automatic data extraction using open BIM (building information modeling) technology [J].
Kim, Hyunjoo ;
Anderson, Kyle ;
Lee, SangHyun ;
Hildreth, John .
AUTOMATION IN CONSTRUCTION, 2013, 35 :285-295
[18]   Framework for Automated Generation of Constructible Steel Erection Sequences Using Structural Information of Static Indeterminacy Variation in BIM [J].
Kim, Kyungki ;
Park, JeeWoong ;
Cho, Chunhee .
KSCE JOURNAL OF CIVIL ENGINEERING, 2020, 24 (11) :3169-3178
[19]   Feasibility study of 4D CAD in commercial construction [J].
Koo, B ;
Fischer, M .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2000, 126 (04) :251-260
[20]   A CBR-based hybrid model for predicting a construction duration and cost based on project characteristics in multi-family housing projects [J].
Koo, ChoongWan ;
Hong, TaeHoon ;
Hyun, ChangTaek ;
Koo, KyoJin .
CANADIAN JOURNAL OF CIVIL ENGINEERING, 2010, 37 (05) :739-752