BIM-based schedule generation and optimization using genetic algorithms

被引:9
作者
Wefki, Hossam [1 ]
Elnahla, Mohamed [1 ]
Elbeltagi, Emad [2 ,3 ]
机构
[1] Port Said Univ, Fac Engn, Civil Engn Dept, Port Said 42526, Egypt
[2] Qassim Univ, Coll Engn, Dept Civil Engn, Buraydah 51452, Saudi Arabia
[3] Mansoura Univ, Fac Engn, Struct Engn Dept, Mansoura 35516, Egypt
关键词
Building information modeling (BIM); Automation; Genetic algorithm; Automatic Scheduling; Construction; Optimization; Integrated project delivery (IPD); 5D simulation; 4D CAD; CONSTRUCTION; MANAGEMENT; SYSTEM;
D O I
10.1016/j.autcon.2024.105476
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
This research presents a transformative framework to tackle challenges within the construction industry, where efficiency is hindered by limited digitalization and disjointed project phases. The framework seamlessly integrates state-of-the-art technologies, such as Building Information Modeling (BIM), Genetic Algorithms (GAs) for schedule optimization, 5D simulation, and a Business Intelligence (BI) Dashboard. By doing so, it effectively enhances productivity while bridging the gap between the realms of management and engineering. A comprehensive literature review underpins the framework's design, focusing mainly on BIM-based schedule generation and optimization. The approach's validity is demonstrated through a compelling case study, showcasing automated BIM model creation, BIM-Based schedule generation limited to structural elements of bottom-up Cast-insitu construction method, GAs-driven schedule optimization, 5D project simulation, and the integration of the BI dashboard. This research propels operational efficiency and promotes harmonious integration with pre-existing software systems, thus facilitating smoother adoption and adaptation.
引用
收藏
页数:22
相关论文
共 49 条
[1]  
Altun M., 2019, A Method for Facilitating 4D Modeling by Automating Task Information Generation and Mapping, P479, DOI [10.1007/978-3-030-00220-6_57, DOI 10.1007/978-3-030-00220-6_57]
[2]  
[Anonymous], 2012, P 2012 WINT SIM C WS, DOI DOI 10.1109/WSC.2012.6465232
[3]   Transforming project delivery: integrated project delivery [J].
Ashcraft, Howard .
OXFORD REVIEW OF ECONOMIC POLICY, 2022, 38 (02) :369-384
[4]   4D dynamic construction management and visualization software: 1. Development [J].
Chau, KW ;
Anson, M ;
Zhang, JP .
AUTOMATION IN CONSTRUCTION, 2005, 14 (04) :512-524
[5]   BIM-based framework for automatic scheduling of facility maintenance work orders [J].
Chen, Weiwei ;
Chen, Keyu ;
Cheng, Jack C. P. ;
Wang, Qian ;
Gan, Vincent J. L. .
AUTOMATION IN CONSTRUCTION, 2018, 91 :15-30
[6]  
Chevallier N, 1998, CAN J CIVIL ENG, V25, P1059
[7]   Generation of a construction planning from a 3D CAD model [J].
de Vries, Bauke ;
Harink, Jeroen M. J. .
AUTOMATION IN CONSTRUCTION, 2007, 16 (01) :13-18
[8]  
Dzeng R.-J., 1995, Ph.D
[9]   Developing a framework to revolutionise the 4D BIM process: IPD-based solution [J].
Elghaish, Faris ;
Abrishami, Sepehr .
CONSTRUCTION INNOVATION-ENGLAND, 2020, 20 (03) :401-420
[10]   Automated BIM schedule generation approach for solving time-cost trade-off problems [J].
ElMenshawy, Mohamed ;
Marzouk, Mohamed .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2021, 28 (10) :3346-3367