A tensioning control method for stay cables with super large tonnage cable force

被引:2
作者
Wang, Lifeng [1 ]
Zhang, Yi [1 ]
Xiao, Ziwang [1 ]
Liu, Long [1 ,2 ]
机构
[1] Northeast Forestry Univ, Sch Civil Engn & Transportat, Harbin, Peoples R China
[2] Anyang Inst Technol, Anyang, Peoples R China
关键词
Cable-stayed bridge; Large tonnage cable force; Single-strand tensioning; Cable force control; CONSTRUCTION; OPTIMIZATION; BRIDGES;
D O I
10.1108/IJSI-12-2023-0149
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
PurposeEffectively solving the large tonnage cable in the construction process due to the tensioning method of the inclined cable often appears in the overall cable force and the design value of the deviation is large, cable internal strand force is not uniform, the main girder stress exceeds the limit of the problem affecting the safety of the structure.Design/methodology/approachIn this study, the finite element method and theoretical analysis method are utilized to propose a construction control method of tensioning the whole bunch of diagonal cables in two parts according to the deformation coordination relationship between the main girder and the diagonal cables. This methodology was implemented during the actual construction of the PAIRA Bridge in Bangladesh.FindingsTests conducted on cable-stayed bridges using this controlled tensioning method demonstrate that the measured cable strength of a single strand exhibits an error of less than 0.15% compared to the design target cable strength. The deviation between the measured and designed cable forces ranges from 0.16% to 0.27%. Furthermore, no tensile stress is observed in both the top plate and bottom plate of the root section of the main girder, indicating a state of full-section compression throughout the entire construction process.Originality/valueThrough the comparison with the test value, it can be proved that the whole bunch of diagonal cable tensioned in two parts of the construction control method proposed in this paper can make the internal strand force more uniform, to meet the precision requirements of the site construction, to protect the safety of the bridge construction process. The method proposed in this paper is highly accurate, easy to calculate, and has a high value of popularization and application.
引用
收藏
页码:613 / 630
页数:18
相关论文
共 32 条
[1]  
American national standards, 2017, AASHTO LRFD BRIDG DE
[2]   A New Multiconstraint Method for Determining the Optimal Cable Stresses in Cable-Stayed Bridges [J].
Asgari, B. ;
Osman, S. A. ;
Adnan, A. .
SCIENTIFIC WORLD JOURNAL, 2014,
[3]   Optimization of Pre-Tensioning Cable Forces in Highly Redundant Cable-Stayed Bridges [J].
Asgari, Banafsheh ;
Osman, Siti Aminah ;
Bin Adnan, Azlan .
INTERNATIONAL JOURNAL OF STRUCTURAL STABILITY AND DYNAMICS, 2015, 15 (01)
[4]   Determination of initial cable forces in prestressed concrete cable-stayed bridges for given design deck profiles using the force equilibrium method [J].
Chen, DW ;
Au, FTK ;
Tham, LG ;
Lee, PKK .
COMPUTERS & STRUCTURES, 2000, 74 (01) :1-9
[5]  
Chen Z.R., 2013, TRANSPORTATION SCI T, P36
[6]  
Fan L., 1992, J. Chongqing Jiaotong Univ, V11, P1
[7]   Construction sequence analysis of long-span cable-stayed bridges [J].
Granata, Michele Fabio ;
Longo, Giuseppe ;
Recupero, Antonino ;
Arici, Marcello .
ENGINEERING STRUCTURES, 2018, 174 :267-281
[8]  
Han R., 2023, Bridge Constr, V53, P97
[9]   Determination of optimum post-tensioning cable forces of cable-stayed bridges [J].
Hassan, M. M. ;
Nassef, A. O. ;
El Damatty, A. A. .
ENGINEERING STRUCTURES, 2012, 44 :248-259
[10]   Estimating tension of a prestressed concrete cable-stayed bridge under construction and traffic use conditions using a vision-based system [J].
Kim, Sung-Wan ;
Park, Dong-Uk ;
Kim, Jin-Soo ;
Park, Jae-Bong .
STRUCTURES, 2023, 47 :299-312