Lean Modular Integrated Construction Production Phase Planning under Uncertainties: A Big Data-Driven Optimization Approach

被引:3
作者
Yang, Zhongze [1 ]
Lu, Weisheng [1 ]
机构
[1] Univ Hong Kong, Dept Real Estate & Construct, Pokfulam, Hong Kong 999077, Peoples R China
关键词
Modular integrated construction (MiC); Production process optimization; Production phase planning; Data-driven optimization; Decision-making under uncertainties; Lean construction; PERFORMANCE; FRAMEWORK; SITE;
D O I
10.1061/JCEMD4.COENG-14420
中图分类号
TU [建筑科学];
学科分类号
0813 ;
摘要
Phase planning is one of the most important components of lean-based production planning that provides basic guidelines for the entire production process. In modular integrated construction (MiC) projects, the complicated and drawn-out features of the manufacturing or production process pose difficulties for informed phase planning decisions under uncertainties. However, owing to the nascent nature of MiC, traditional approaches have little prior knowledge of the uncertainties. This research aimed to address this problem by proposing a data-driven optimization method based on a set of valuable historical production data to hedge against uncertainties during production. A real-life case study was then conducted to validate this optimization approach. The planning solution, including the (1) critical production path, (2) detailed production schedules, and (3) simulated production process, balances production schedules and uncertainties to ensure feasible and robust phase planning. This optimization method can make full use of historical production data rather than approximations of the probability distributions to handle uncertainties in the phase planning process. This research provides an innovative and robust solution for MiC production managers to efficiently conduct phase planning under uncertainties. It enriches the literature on phase planning and contributes to lean MiC manufacturing. The biggest novelty of this research is to open up a window for researchers and practitioners to look into MiC production in factories, which are traditionally like a "black box" unknown to us.
引用
收藏
页数:14
相关论文
共 50 条
[1]   Improving construction management practice with the Last Planner System: a case study [J].
AlSehaimi, Abdullah ;
Fazenda, Patricia ;
Koskela, Lauri .
ENGINEERING CONSTRUCTION AND ARCHITECTURAL MANAGEMENT, 2014, 21 (01) :51-+
[2]   Analysis of interacting uncertainties in on-site and off-site activities: Implications for hybrid construction [J].
Arashpour, Mehrdad ;
Wakefield, Ron ;
Lee, E. W. M. ;
Chan, Ricky ;
Hosseini, M. Reza .
INTERNATIONAL JOURNAL OF PROJECT MANAGEMENT, 2016, 34 (07) :1393-1402
[3]   Development of Innovative Integrated Last Planner System (ILPS) [J].
Aslam, Mughees ;
Gao, Zhili ;
Smith, Gary .
INTERNATIONAL JOURNAL OF CIVIL ENGINEERING, 2020, 18 (6A) :701-715
[4]   Applying lean thinking in construction and performance improvement [J].
Aziz, Remon Fayek ;
Hafez, Sherif Mohamed .
ALEXANDRIA ENGINEERING JOURNAL, 2013, 52 (04) :679-695
[5]   The role of optimization in some recent advances in data-driven decision-making [J].
Baardman, Lennart ;
Cristian, Rares ;
Perakis, Georgia ;
Singhvi, Divya ;
Lami, Omar Skali ;
Thayaparan, Leann .
MATHEMATICAL PROGRAMMING, 2023, 200 (01) :1-35
[6]  
Ballard H., 2000, The Last Planner System of Production Control
[7]  
Bernoulli J., 1713, Thurnisiorum
[8]  
Bertsimas D., 2006, Tutorials in Operations Research, P95, DOI DOI 10.1287/EDUC.1063.0022
[9]   Adaptive Distributionally Robust Optimization [J].
Bertsimas, Dimitris ;
Sim, Melvyn ;
Zhang, Meilin .
MANAGEMENT SCIENCE, 2019, 65 (02) :604-618
[10]   Theory and Applications of Robust Optimization [J].
Bertsimas, Dimitris ;
Brown, David B. ;
Caramanis, Constantine .
SIAM REVIEW, 2011, 53 (03) :464-501