Joint effect of commodity price and geological uncertainty over the life of mine and ultimate pit limit

被引:13
作者
Del Castillo, Fernanda [1 ]
Dimitrakopoulos, Roussos [1 ]
机构
[1] McGill Univ, Dept Min & Mat Engn, COSMO Stochast Mine Planning Lab, Montreal, PQ, Canada
来源
TRANSACTIONS OF THE INSTITUTIONS OF MINING AND METALLURGY SECTION A-MINING TECHNOLOGY | 2014年 / 123卷 / 04期
基金
加拿大自然科学与工程研究理事会;
关键词
Stochastic mine planning; Real options; Price forecasting; Life of mine;
D O I
10.1179/1743286314Y.0000000069
中图分类号
TD [矿业工程];
学科分类号
0819 ;
摘要
Mining operations are highly affected by risk, commodity price and geology being acknowledged as the most relevant risk factors. Considering these uncertainties at an early stage is a key element of project success, and doing so by including annual re-evaluations of a project allows for a more realistic approach. A real-options based evaluation is presented herein to assess the effects of uncertainty over the life of an open pit mining operation and the consequent ultimate pit limit modifications. A case study at a gold mine shows the value of having flexibility to expand or stop mining early when dealing with stochastic scenarios of both the deposit being assessed and the related commodity prices. Stochastic scenarios provide useful probabilistic data that traditional methods ignore, in spite of the fact that they have a major effect on optimal pit limits and mine design. A geometric Brownian motion with Poisson jumps model is used to forecast price, and direct block simulation (DBSim) is used to model geological uncertainty. The proposed model is optimized using the commercial software ILOG-Cplex; results show that including the option to stop mining or expand increases the operation's value, allowing management to assess mine designs and prepare for changes that may have substantial ramifications.
引用
收藏
页码:207 / 219
页数:13
相关论文
共 63 条
[1]   Valuing real capital investments using the least-squares Monte Carlo method [J].
Abdel Sabour, Sabry A. ;
Poulin, Richard .
Engineering Economist, 2006, 51 (02) :141-160
[2]  
Albor Consuegra F., 2010, IMM T MIN TECHNOL, V119, P68
[3]  
Amram M., 1999, REAL OPTIONS MANAGIN, P240
[4]   Optimum cut-off grade policy for open pit mining operations through net present value algorithm considering metal price and cost escalation [J].
Asad, M. W. A. .
ENGINEERING COMPUTATIONS, 2007, 24 (7-8) :723-736
[5]   Implementing a parametric maximum flow algorithm for optimal open pit mine design under uncertain supply and demand [J].
Asad, M. W. A. ;
Dimitrakopoulos, R. .
JOURNAL OF THE OPERATIONAL RESEARCH SOCIETY, 2013, 64 (02) :185-197
[6]   Optimal production scale of open pit mining operations with uncertain metal supply and long-term stockpiles [J].
Asad, Mohammad Waqar Ali ;
Dimitrakopoulos, Roussos .
RESOURCES POLICY, 2012, 37 (01) :81-89
[7]   PRICING OF OPTIONS AND CORPORATE LIABILITIES [J].
BLACK, F ;
SCHOLES, M .
JOURNAL OF POLITICAL ECONOMY, 1973, 81 (03) :637-654
[8]  
Blanco C., 2001, COMMOD NOW ENERGY PR, V1, P74
[9]  
Blanco C., 2001, COMMODITIES NOW, V2, P83
[10]   Geometallurgical Modeling at Olympic Dam Mine, South Australia [J].
Boisvert, Jeff B. ;
Rossi, Mario E. ;
Ehrig, Kathy ;
Deutsch, Clayton V. .
MATHEMATICAL GEOSCIENCES, 2013, 45 (08) :901-925