Evaluation of non-cost factors affecting the life cycle cost: an exploratory study

被引:10
作者
Alqahtani, Ayedh [1 ]
Whyte, Andrew [1 ]
机构
[1] Curtin Univ, Dept Civil Engn, Perth, WA, Australia
关键词
Cost estimation; Questionnaire survey; Multiple-regression; Building projects; Life cycle cost; Non-cost factors;
D O I
10.1108/JEDT-02-2015-0005
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Purpose - This paper aims to identify the main non-cost factors affecting accurate estimation of life cycle cost (LCC) in building projects. Design/methodology/approach - Ten factors affecting LCC in building project cost estimates are identified through literature and interviews. A questionnaire survey is conducted to rank these factors in order of priority and provide the views of cost practitioners about the significance of these factors in the accurate estimation of LCC. The data from 138 construction building projects completed in UK were collected and analysed via multiple regression to discover the relationship between capital and LCCs and between non-cost factors and cost estimation at each stage of the life cycle (capital, operation, maintenance and LCC). Findings - The results of analysis of existing LCC data of completing project and survey data from cost professionals are mostly consistent with many literature views and provide a reasonable description of the non-cost factors affecting the accuracy of estimates. Originality/value - The value of this study is in the method used, which involves analysis of existing life data and survey data from cost professionals. The results provide a plausible description of the non-cost factors affecting the accuracy of estimates.
引用
收藏
页码:818 / 834
页数:17
相关论文
共 38 条
[1]   The accuracy of pre-tender building cost estimates in Australia [J].
Aibinu, Ajibade Ayodeji ;
Pasco, Thomas .
CONSTRUCTION MANAGEMENT AND ECONOMICS, 2008, 26 (12) :1257-1269
[2]  
Akintoye A., 2000, CONSTRUCTION MANAGEM, V18, P77, DOI DOI 10.1080/014461900370979
[3]  
Al- Hajj A., 1991, SIMPLE COST SIGNIFIC
[4]   Artificial Neural Networks Incorporating Cost Significant Items towards Enhancing Estimation for (life-cycle) Costing of Construction Projects [J].
Alqahtani, Ayedh ;
Whyte, Andrew .
CONSTRUCTION ECONOMICS AND BUILDING, 2013, 13 (03) :51-64
[5]  
Alum J., 1995, INT J PROJ MANAG, V13, P51, DOI DOI 10.1016/0263-7863(95)95704-H
[6]   A case-based reasoning cost estimating model using experience by analytic hierarchy process [J].
An, Sung-Hoon ;
Kim, Gwang-Hee ;
Kang, Kyung-In .
BUILDING AND ENVIRONMENT, 2007, 42 (07) :2573-2579
[7]  
Arafa M., 2011, J ARTIF INTELL, V4, P63, DOI [10.3923/jai.2011.63.75, DOI 10.3923/JAI.2011.63.75]
[8]  
Ashworth A., 2010, COST STUDIES BUILDIN
[9]   A life cycle cost based approach of O&M support for mechanical systems [J].
Asjad M. ;
Kulkarni M.S. ;
Gandhi O.P. .
International Journal of System Assurance Engineering and Management, 2013, 4 (2) :159-172
[10]   Predicting cost deviation in reconstruction projects: Artificial neural network versus regression [J].
Attalla, M ;
Hegazy, T .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT-ASCE, 2003, 129 (04) :405-411