Effects of Change Orders on Cost Growth, Schedule Growth, and Construction Intensity of Large Highway Projects

被引:36
作者
Shrestha, Pramen P. [1 ]
Maharjan, Ruiko [1 ]
机构
[1] Univ Nevada, Civil & Environm Engn & Construct, Howard R Hughes Coll Engn, Las Vegas, NV 89154 USA
关键词
Change order growth; Number of change orders; Texas Department of Transportation; Correlation;
D O I
10.1061/(ASCE)LA.1943-4170.0000264
中图分类号
D9 [法律]; DF [法律];
学科分类号
0301 ;
摘要
Previous research have shown that change orders have a detrimental effect on cost growth and schedule growth of construction projects. These studies mainly concentrated on the number of change orders for building or maintenance projects. However, correlation of the number and change order growth with cost growth, schedule growth, and construction intensity of new highway projects has not been studied. This study collected data from 185 projects from the state of Texas, whose costs amounted to more than $10M. The results showed that the average change order growth for these projects was 7.0%, and also found a significant positive correlation in change order growth with cost growth and schedule growth of these projects. The correlation coefficients of change order growth with cost growth and schedule growth were found to be 0.57 and 0.44, respectively. When the projects were divided into two groups based on the change order growth, the results showed that the cost growth and schedule growth significantly increased as the change order growth increased to greater than 5%. The number of change orders were significantly and positively correlated with cost growth (0.23), schedule growth (0.30), and construction intensity (0.46). When the number of change orders increased by more than 20, then the cost and schedule growth increased significantly. It is recommended that Texas Department of Transportation engineers use an effective change management process to control the change orders in their highway projects so that cost and schedule overruns could be minimized. (C) 2018 American Society of Civil Engineers.
引用
收藏
页数:9
相关论文
共 25 条
[1]  
Abdullah, 2009, J ENG APPL SCI, V4, P170
[2]   Causes, Effects, Benefits, and Remedies of Change Orders on Public Construction Projects in Oman [J].
Alnuaimi, Ali S. ;
Taha, Ramzi A. ;
Al Mohsin, Mohammed ;
Al-Harthi, Ali S. .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2010, 136 (05) :615-622
[3]   Frequency of Change Orders in Highway Construction Using Alternate Count-Data Modeling Methods [J].
Anastasopoulos, Panagiotis Ch. ;
Labi, Samuel ;
Bhargava, Abhishek ;
Bordat, Claire ;
Mannering, Fred .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2010, 136 (08) :886-893
[4]   Causes of delay in large construction projects [J].
Construction Engineering and Management Department, King Fahd University of Petroleum and Minerals, Box # 680, Dhahran, 31261, Saudi Arabia .
Int. J. Proj. Manage., 2006, 4 (349-357) :349-357
[5]  
Bordat C., 2004, FHWAINJTRP20047 TRAN
[6]   Time-Cost Performance Effect of Change Orders from Accelerated Contract Provisions [J].
Choi, Kunhee ;
Lee, Hyun Woo ;
Bae, Junseo ;
Bilbo, David .
JOURNAL OF CONSTRUCTION ENGINEERING AND MANAGEMENT, 2016, 142 (03)
[7]  
CII (Construction Industry Institute), 2017, CHANGE MANAGEMENT
[8]  
Dickson O.D., 2015, INT J ENG RES TECHNO, V4, P1124
[9]  
Dummies: A Wiley Brand, 2018, INT CORR COEFF R
[10]  
Emadelbeltagi A. A., 2014, J ENG RES APPL, V4