Scheduling maintenance optimization of power systems using ant colonies

被引:0
作者
Hadjri, S. [1 ]
Zeblah, A. [2 ]
Ghoraf, A. [3 ]
Massim, Y. [4 ]
Meziane, R. [5 ]
Hamdaoui, H. [2 ]
机构
[1] Univ Djillali Liabes Sidi Bel Abbes, Dept Elect, BP 89, Sidi Jilali, Algeria
[2] Univ Djillali Liabes Sidi Bel Abbes, Dept Elect Engn, Sidi Jilali, Algeria
[3] Univ Sherbrooke, Dept Mathemat & Informat, Sherbrooke, PQ J1K 2R1, Canada
[4] Univ Djillali Liabes Sidi Bel Abbes, Dept Phys, Sidi Jilali, Algeria
[5] Univ SAIDA, Dept Elect Engn, En Nasr, Algeria
关键词
Ant colonies; optimization; preventive maintenance; universal generating function;
D O I
10.1080/02522667.2007.10699758
中图分类号
G25 [图书馆学、图书馆事业]; G35 [情报学、情报工作];
学科分类号
1205 ; 120501 ;
摘要
This paper addresses an ant colony meta-heuristic optimization method to solve a preventive maintenance (PM) problem for series-parallel system. In this work, we consider the situation where system and its components have several ranges of performance levels. Such systems are called multi-state systems (MSS). To enhance system availability or (reliability), possible schedule preventive maintenance actions are performed to equipments and affect strongly the effective age. The MSS measure is related to the ability of the system to satisfy the demand. The objective is to develop an algorithm to generate an optimal sequence of maintenance actions providing system working with the desired level of availability or (reliability) during its lifetime with minimal maintenance cost rate. To evaluate the multistate system availability, a fast method based on the universal moment generating function (UMGF) is suggested. The ant colony approach can be applied as an optimization technique and adapted to this PM optimization problem.
引用
收藏
页码:523 / 539
页数:17
相关论文
共 21 条
[1]  
BILLINTON R, 1990, RELIABILITY EVALUATI
[2]   A Monte Carlo methodological approach to plant availability modeling with maintenance, aging and obsolescence [J].
Borgonovo, E ;
Marseguerra, M ;
Zio, E .
RELIABILITY ENGINEERING & SYSTEM SAFETY, 2000, 67 (01) :61-73
[3]   IMPERFECT REPAIR [J].
BROWN, M ;
PROSCHAN, F .
JOURNAL OF APPLIED PROBABILITY, 1983, 20 (04) :851-859
[4]   ON THE COMPUTATIONAL-COMPLEXITY OF RELIABILITY REDUNDANCY ALLOCATION IN A SERIES SYSTEM [J].
CHERN, MS .
OPERATIONS RESEARCH LETTERS, 1992, 11 (05) :309-315
[5]   Ant system: Optimization by a colony of cooperating agents [J].
Dorigo, M ;
Maniezzo, V ;
Colorni, A .
IEEE TRANSACTIONS ON SYSTEMS MAN AND CYBERNETICS PART B-CYBERNETICS, 1996, 26 (01) :29-41
[6]   DEGRADABLE SYSTEMS - A SURVEY OF MULTISTATE SYSTEM-THEORY [J].
ELNEWEIHI, E ;
PROSCHAN, F .
COMMUNICATIONS IN STATISTICS-THEORY AND METHODS, 1984, 13 (04) :405-432
[7]  
Gude D., 1993, International Journal of Human Factors in Manufacturing, V3, P335, DOI 10.1002/hfm.4530030403
[8]   Structure optimization of power system with different redundant elements [J].
Levitin, G ;
Lisnianski, A ;
Elmakis, D .
ELECTRIC POWER SYSTEMS RESEARCH, 1997, 43 (01) :19-27
[9]   Redundancy optimization for series-parallel multi state systems [J].
Levitin, G ;
Lisnianski, A ;
Ben-Haim, H ;
Elmakis, D .
IEEE TRANSACTIONS ON RELIABILITY, 1998, 47 (02) :165-172
[10]   Optimal multistage modernization of power system subject to reliability and capacity requirements [J].
Levitin, G ;
Lisnianski, A .
ELECTRIC POWER SYSTEMS RESEARCH, 1999, 50 (03) :183-190