An Approach to Locate an In Pit Crusher in Open Pit Mines

被引:23
|
作者
Rahmanpour, M. [1 ]
Osanloo, M. [1 ]
Adibee, N. [1 ]
AkbarpourShirazi, M. [2 ]
机构
[1] Amirkabir Univ Technol, Dept Min & Met Engn, Tehran, Iran
[2] Amirkabir Univ Technol, Dept Ind Engn & Management Sci, Tehran, Iran
来源
INTERNATIONAL JOURNAL OF ENGINEERING | 2014年 / 27卷 / 09期
关键词
Open Pit Mining; In Pit Crushing and Conveying; Hub Location Problem;
D O I
10.5829/idosi.ije.2014.27.09c.18
中图分类号
T [工业技术];
学科分类号
08 ;
摘要
Haulage costs accounts for 45 to 60% of the total operating costs in large open pit mines. Cost efficiency and high reliability of semi mobile or combined "In Pit Crushing-Conveying (IPCC) and truck" systems compared to conventional truck-shovel systems alone, makes it more appealing to be utilized in modern mining activities. Semi mobile systems have the advantages of both systems, and its operating costs depend on the location of the in pit crushing unit. In this paper, the effective factors on determination of a suitable location of an IPCC are studied and it is investigated as a single hub location problem. The main concerns of the optimum location are minimizing haulage costs and choosing a location regarding the environmental concerns. The method is applied in Sarcheshmeh Copper Mine (SCM), and according to the results, locations C1 to C4 are candidate locations, and applying the hub model, location C2 on level 2450 is suggested to locate the IPCC.
引用
收藏
页码:1475 / 1484
页数:10
相关论文
共 50 条
  • [1] A heuristic approach for in-pit crusher and conveyor system's time and location problem in large open-pit mining
    Paricheh, Morteza
    Osanloo, Morteza
    Rahmanpour, Mehdi
    INTERNATIONAL JOURNAL OF MINING RECLAMATION AND ENVIRONMENT, 2018, 32 (01) : 35 - 55
  • [2] Production scheduling optimization in open pit mines
    Fytas, K.
    Hadjigeorgiou, J.
    Collins, J.L.
    International journal of surface mining & reclamation, 1993, 7 (01): : 1 - 9
  • [3] Choosing an Optimal Groundwater Lowering Technique for Open Pit Mines
    Golestanifar, Mojtaba
    Ahangari, Kaveh
    MINE WATER AND THE ENVIRONMENT, 2012, 31 (03) : 192 - 198
  • [4] TOWARD A RECLAMATION EFFORT ESTIMATION PROCEDURE FOR OPEN PIT MINES
    Chmykhalov, S. V.
    EURASIAN MINING, 2023, (01): : 83 - 85
  • [5] Short-term planning for open pit mines: a review
    Blom, Michelle
    Pearce, Adrian R.
    Stuckey, Peter J.
    INTERNATIONAL JOURNAL OF MINING RECLAMATION AND ENVIRONMENT, 2019, 33 (05) : 318 - 339
  • [6] ON IMPROVING TRUCK SHOVEL PRODUCTIVITY IN OPEN-PIT MINES
    WHITE, JW
    OLSON, JP
    VOHNOUT, SI
    CIM BULLETIN, 1993, 86 (973): : 43 - 49
  • [7] A New Approach to Optimize Ultimate Geometry of Open Pit Mines with Variable Overall Slope Angles
    Altuntov, Firdevs Kubra
    Erkayaoglu, Mustafa
    NATURAL RESOURCES RESEARCH, 2021, 30 (06) : 4047 - 4062
  • [8] A New Approach to Optimize Ultimate Geometry of Open Pit Mines with Variable Overall Slope Angles
    Firdevs Kübra Altuntov
    Mustafa Erkayaoğlu
    Natural Resources Research, 2021, 30 : 4047 - 4062
  • [9] Mining Complexity Assessment to Substantiate Deformation Monitoring at Open Pit Mines
    Ponomarenko, M. R.
    Kutepov, Yu, I
    JOURNAL OF MINING SCIENCE, 2021, 57 (06) : 986 - 994
  • [10] Real-time truck dispatching in open-pit mines
    Wang, Xiaowei
    Dai, Qi
    Bian, Yougang
    Xie, Guotao
    Xu, Biao
    Yang, Zeyu
    INTERNATIONAL JOURNAL OF MINING RECLAMATION AND ENVIRONMENT, 2023, 37 (07) : 504 - 523