AN INVENTORY MODEL OF INCENTIVES FOR ON-TIME DELIVERY IN JUST-IN-TIME PURCHASING CONTRACTS

被引:0
作者
GROUT, JR [1 ]
CHRISTY, DP [1 ]
机构
[1] PENN STATE UNIV,SMEAL COLL BUSINESS ADM,DEPT MANAGEMENT SCI & INFORMAT SYST,UNIV PK,PA 16802
关键词
D O I
10.1002/1520-6750(199310)40:6<863::AID-NAV3220400609>3.0.CO;2-1
中图分类号
C93 [管理学]; O22 [运筹学];
学科分类号
070105 ; 12 ; 1201 ; 1202 ; 120202 ;
摘要
This article formulates an analytic model of just-in-time purchasing contracts and compares the minimum cost solution with the cost attainable through vertical integration. The models use standard inventory theory cost parameters and decision variables. The results quantify the increase in cost of buying an item rather than making it. Optimal incentives are characterized when JIT purchasing contracts are used. When JIT purchasing is implemented, buffer inventories are typically reduced. This inventory reduction makes on-time delivery critical to the buyer; yet timeliness is controlled by the supplier. As an incentive to provide on-time delivery, the buyer offers the supplier a bonus for on-time delivery. The supplier chooses a flow time allowance based upon the bonus offered. First- and second-order conditions are characterized in general, and examples are provided for exponentially and uniformly distributed flow times. The delivery timeliness obtainable in a vertically integrated firm is determined and compared with timeliness obtainable between separate firms. This comparison indicates that buyers who choose to purchase materials from a separate firm are more likely to experience late deliveries. The relationship between the value of the bonus and the proportion of on-time deliveries is also considered. The bonus required to achieve the same probability of on-time delivery as under vertical integration is also determined. (C) 1993 John Wiley & Sons, Inc.
引用
收藏
页码:863 / 877
页数:15
相关论文
共 15 条
[1]  
[Anonymous], PRODUCTION INVENTORY
[2]  
CELLEY AF, 1987, J PURCHASING MATERIA, P9
[4]  
CRAWFORD KM, 1988, INT J PROD RES, V26, P1561, DOI 10.1080/00207548808947966
[5]   MITIGATING CONTRACTUAL HAZARDS - UNILATERAL OPTIONS AND CONTRACT-LENGTH [J].
CROCKER, KJ ;
MASTEN, SE .
RAND JOURNAL OF ECONOMICS, 1988, 19 (03) :327-343
[6]  
FREELAND JR, 1991, PRODUCTION INVENTORY, P43
[7]  
HILL AV, 1986, J OPERATIONS MANAGEM, V6, P381, DOI DOI 10.1016/0272-6963(86)90011-2
[8]  
KANET JJ, 1984, INT J PROD RES, V22, P41, DOI 10.1080/00207548408942428
[9]   A COOPERATIVE GAME-THEORY MODEL OF QUANTITY DISCOUNTS [J].
KOHLI, R ;
PARK, H .
MANAGEMENT SCIENCE, 1989, 35 (06) :693-707
[10]   A GENERALIZED QUANTITY DISCOUNT PRICING MODEL TO INCREASE SUPPLIERS PROFITS [J].
LEE, HL ;
ROSENBLATT, MJ .
MANAGEMENT SCIENCE, 1986, 32 (09) :1177-1185